Regarding Non submission of technical details and samples of materials and accessories
Date : xxx
Ref : CC/DESTEC/004
To : M/s. xxx GROUP, PO Box 47395, Sharjah UAE.
Project : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai
Subject : Regarding Non submission of technical details and samples of materials and accessories
Dear Mr. xxx,
With reference to the above mentioned subject, we would like to intimate you again the submission of technical details and sample board/samples for materials and accessories are still awaited from your side.
As you intimated consultant will take 14 days for reviewing any submittal and revised submittal also same. Without approval of materials you can’t start work at site
So, this is for your kind intimation to submit pending submittal as an earliest possible.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager