Regarding non acceptance of payment terms.

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject        :  Regarding non acceptance of payment terms.

Dear Sir,

With reference above, the nomination dated on 09-07-xxx ref no: AP/269/xxx. We sent the payment terms attaching in the nomination same to send to sub-contractor and their reply attached.

Here with the sub-contractor is not accepting the terms attached in the nomination.

So, we cannot send any LPO until payment terms between nominated sub-contractor and the client will not be resolved.

This is for your kind information and to do needful.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager