Regarding no worker from our end to complete the remaining works and hand over the site

Keys Handing over
Keys Handing over

Date: xxx

Ref. xxx

To:                     M/s. xxx , Metal Wowks

Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject:Regarding no worker from our end to complete the remaining works and hand over the site  

Dear Engr. Mansour ,

With reference to the above, we are hereby intimating you that there is no workers came from your side  for today and you are suspending the works without prior notice or intimation.

So, this is to inform you  that the main contractor will not responsible in any delay happen and no work in progress to complete the pending works and hand over the site from your end.

This is for y our kind information and for the record.

Regards,
For xxx Contracting L.L.C

xxx

Project Manager

By Md Abu Zaed Khan