Date: xxx
Ref. xxx
Kind Attn: Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotels Building
Plot No.: xxx at Al Barsha 1st, Dubai
Subject: Regarding follow up of pending work
Dear Tahir,
With ref. to above, the following are to be submitted to consultant.
- Inclusion/ exclusion items to be submitted
- Long lead item must be submitted by tomorrow
- Cut out drawings must be submitted today (letter ref. no: AP/269/CC/131 dt.31.08.16)
- Shop drawings and material logs to be updates and to be submitted to consultant.
- MEP drawings required for mockup room, which include water supply, exhaust, any ducts or machine and AC drawings for toilets for unit no 5- twin room & unit no 6- queen room which we have considered for mock up room
- New IPTV drawings received from consultant letter ref. no AP/269/CC/158 dt 09.10.16 to be followed.
- Guest room management system – time escalation letter ref. no: AP/269/CC/150 dt.25.09.16
So, kindly resolve all the pending issues.
Regards,
For xxx Contracting L.L.C
xxx
General Manager