Regarding Execution outside RMU room to cut the steel beam

Manhole-Excavation
Manhole-Excavation

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject              :   Regarding Execution outside RMU room to cut the steel beam and encounter the huge concrete.

Dear sir,

With reference to the above mentioned subject,  as per the undertaking letter by M/S xxx to remove all the temporary work during the shoring work. As we are in process to hand over the RMU room, we have done the excavation to clear the trench area and encounter the massive guide wall concrete, which we suspect that this concrete is at  full length of the Project boundary at front side.

Kindly note that during the service connection  either it is Telephone, DEWA, or Drainage, they will not accept the concrete in corridor. This is the responsibility of M/S S.S.LOOTAH 

So this is for your kind information.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version