Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Regarding Execution outside RMU room to cut the steel beam and encounter the huge concrete.
Dear sir,
With reference to the above mentioned subject, as per the undertaking letter by M/S xxx to remove all the temporary work during the shoring work. As we are in process to hand over the RMU room, we have done the excavation to clear the trench area and encounter the massive guide wall concrete, which we suspect that this concrete is at full length of the Project boundary at front side.
Kindly note that during the service connection either it is Telephone, DEWA, or Drainage, they will not accept the concrete in corridor. This is the responsibility of M/S S.S.LOOTAH
So this is for your kind information.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager