Date: xxx
To : xxx Contracting
Kind Attn : Mr. xxx Vangani /Mr. xxx
Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai
Subject : Regarding Confirmation and No –Objection to Remove the Tower Crane Support @ 3rd Flr. and same System and Drawing can be used in 11th Flr. Slab
Dear Sir ,
With reference above, we are confirming that after fixing the support between 6th-7th Flr. We do not required the existing support at 3rd Flr. and same support removed and fixed at 11th Flr. as per attached drawing which is used in 6th Flr. in same.
Furthermore we are confirming that as per joint reaction and design in the drawing is safe and sound to fixed at 11th Flr by using the system from 3rd Flr.
So we are acknowledging and confirming the removal of support at 3rd Flr. and fixing at 11th Flr. for further extension of the Tower Crane.
Regards,
Authorized Signatory