Re. Remaining Engineering Works.
Our Ref: xxx
Date: xxx
To : xxx Construct Company Ltd.
P. O. Box xxx
Abu Dhabi – UAE.
Attention : Eng. xxx
: Project Director
Subject : Re. Remaining Engineering Works.
Dear Mr. xxx,
We acknowledge the receipt of your letter ref. xxx (Aconex ref. xxx) received on 17th October xxx. Please find our response below as requested on 23rd October xxx.
- Shop Drawings:-
Please find the attached updated shop drawings log. Refer appendix 1.
Note: 5 drawings with status ‘ C ’ will be uploaded in Aconex within this week.
- BIM Models, clash reports, etc.:-
This is not under Unipods scope of work.
- Material and sample submissions:-
Please find the attached Material and sample submission log. Refer appendix 2.
- Method statements, and:-
Please find the attached log of the approved MOS under Unipods scope for your information – Refer appendix 3.
- Reports/calculations:-
Please find the attached latest project update reports. Refer appendix 4.
We trust the above clarification can be fulfil your requirements.
This is for your information and record.
On behalf of xxx LLC
xxx
Projects Manager