Shop Drawing

Re. B-Status Comments

Our Ref: xxx

Date: xxx

To                    :           xxx Construction Co. L.L.C.

                                    P. O. Box xxx

            Dubai – UAE.

Attention          :           xxx

                        :           Sr. Project Manager

Project             :           xxx Park Hotel Dubai

Subject            :           Re. B-Status Comments

Dear Sir,

We received your letter ref: xxx regarding the B status comments on the submittals. We understand that this is a general memo/notice forwarded to all sub-contractors. However we would like to highlight some points for our record to make it clear for both the parties.

  • Material Submittals

At this point of time we are not able to proceed with the procurement on the materials even if we have the “B” because of the following reasons.

  • We still don’t have an approval on the reference pod delivered to site on 21.05.xxxx.
  • We still don’t have a clear understanding on the other types of pods in this project.
  • We still don’t have an instruction to proceed with the procurement as the design is not approved or finalized.
  • Design Drawings
  • xxx don’t have any drawings under the B status to proceed further.

Hope this is clear and clarifies the situation.

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager