Progress of slab no.12 is stopped due to Full day rain

Progress of slab no.12 is stopped due to Full day rain

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Intimating that Progress of slab no.12 is stopped due to Full day rain on dated xxx

Dear Sir,

With reference to the above, Our progress of the slab no.12 is badly affected due to rain which is the force measure/act of God and this not under control of the contractor

So, slab no.12 being continuously affected because rain is happening in irregular interval and unfortunately today it is raining since morning.

This is for your kind information that we cannot work or operate electrical equipment or any tools to avoid any risk or hazardous condition.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager