Second floor sunken area piping and intimation for filling.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Second floor sunken area piping and intimation for filling. Dear Sir, With reference to the above, Our scope of work for the sunken area which is located at second […]

To release the ID drawing from 3rd floor as well as comments in the tile corner by ID

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject          : To release the ID drawing from 3rd floor as well as comments in the tile corner by ID Dear Sir, With reference to above, we received the ID drawing […]

Response/Concern to your letter ref no: xxx dt: xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Response/Concern to your letter ref no: xxx dt: xxx Dear Sir, With reference to your said communication and inline of reply for the same , Kindly note the following: […]

Progress of slab no.12 is stopped due to Full day rain

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Intimating that Progress of slab no.12 is stopped due to Full day rain on dated xxx Dear Sir, With reference to the above, Our progress of the slab no.12 […]

Submission of renewed CAR policy

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Submission of renewed CAR policy Dear Sir, With reference to the above and as per your letter ref no: xxx dt.xxx & xxx dt.xxx, we are hereby submitting the […]

Finalization or nomination of motion sensor subcontractor in the building

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Regarding finalization/ nomination of motion sensor subcontractor in the building Dear Sir, With reference to the above, as per our contract documents and our exclusion which is part of […]

Regarding shifting the tower crane support from 3rd floor to 11th floor

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Regarding shifting the tower crane support from 3rd floor to 11th floor Dear Sir, With reference to the above, we are intimating that, we must shift the tower crane […]

Regarding issue of the joinery nominations

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject            : Regarding issue of the joinery nominations (your ref no. xx) Dear Sir, With reference to the above, we have received your letter with ref no:AP/269/293 dated 14.02.17 with the […]

Regarding Bathtub Areas Internal Dimensions Re-Confirmation

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Subject:          Regarding Bathtub Areas Internal Dimensions Re-Confirmation Dear Sir, We are conforming the inner dimension of the toilet wherever the bathtub is required  and kindly note the following: 1. The bathtub […]

Reply to your letter Ref: xxx Dated xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E. Dear Sir, With reference to your letter Ref: AP/269/CC/246 Dated 19.02.2017, kindly note that the Contractor Claim as per FIDIC 4th Edition reprinted in 1992, “Clause 44.(c)”, Contractor is entitled to […]