Confirmation to replace the 13 marble sets in case commented by the Home Owners

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Confirmation to replace the 13 marble sets in case commented by the Home Owners Reference:  a) UP-1747/LET-1370-22/LS-at dated 04 March xxx                     … Continue reading Confirmation to replace the 13 marble sets in case commented by the Home Owners

RE- Notice of misuse, damage & theft/loss of materials from pods on site

Sanitary Accessories

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     RE– Notice of misuse, damage & theft/loss of materials from pods on site References:  a) xxx dated 6 July xxx                         b)… Continue reading RE- Notice of misuse, damage & theft/loss of materials from pods on site

Additional cost for rectification of damaged works

Running Cost

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Additional cost for rectification of damaged works Reference:  a) xxx dated 23 March xxx Dear Sir, We are in receipt of your… Continue reading Additional cost for rectification of damaged works

LED strip light connectors & closure of NCR-ELECT-001

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     LED strip light connectors & closure of NCR-ELECT-001 Dear Sir, We are writing to you following our previous Email (appendix 1) with… Continue reading LED strip light connectors & closure of NCR-ELECT-001

RE- damage / loss reports for pods on site

report

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     RE– damage / loss reports for pods on site Reference:  a) UP‐1747/LET‐1216‐21/LS‐at dated 6 July xxx                       b) UP‐1747/LET‐1220‐21/LS‐at dated 6 July… Continue reading RE- damage / loss reports for pods on site

Confirmation to replace the 13 marble sets in case commented by the Home Owners

Marble Vanity Top

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Confirmation to replace the 13 marble sets in case commented by the Home Owners Reference: a) xxx dated 04 March xxx Dear… Continue reading Confirmation to replace the 13 marble sets in case commented by the Home Owners

Notice of misuse, damage & loss of materials on site

Pods Damaged by other at site

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Notice of misuse, damage & loss of materials on site Reference:  a) xxx dated 06 July xxx                       b) xxx dated 06… Continue reading Notice of misuse, damage & loss of materials on site

Notice of misuse, damage & theft/loss of materials from pods on site

Sanitary Accessories

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Notice of misuse, damage & theft/loss of materials from pods on site Reference:  a) xxx‐at dated 6 July xxx                       b) xxx… Continue reading Notice of misuse, damage & theft/loss of materials from pods on site

Request to relook into the finishing inspection status for 13 pods

shake-up-sales-meeting

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Request to relook into the finishing inspection status for 13 pods Dear Sir, We are writing to request you to kindly relook… Continue reading Request to relook into the finishing inspection status for 13 pods

RE – Project Closing out documents – Meeting

delivery of Tiles and cheque copy.

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     RE – Project Closing out documents – Meeting Dear Sir, We are in receipt of your two letters ref: xxx and xxx… Continue reading RE – Project Closing out documents – Meeting