Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Response to Notice of delay in finalizing walls & floor tiles. References: xxx dated 13 July xxx xxx dated 04… Continue reading Response to Notice of delay in finalizing walls & floor tiles.
Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations Dear Sir, As per the instructions received during site coordination… Continue reading Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations
Rejection to Notice of Delay
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Rejection to Notice of Delay References: a) xxx dated 21 June xxx b) xxx dated 06 July xxx c)… Continue reading Rejection to Notice of Delay
Response to Notice of delay in finalizing walls & floor tiles.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Response to Notice of delay in finalizing walls & floor tiles. Dear Sir, We are in receipt of your letter ref:… Continue reading Response to Notice of delay in finalizing walls & floor tiles.
Rejection to Notice of Delay
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Rejection to Notice of Delay References: a) xxx dated 21 June xxx b) xxx dated 06 July xxx c)… Continue reading Rejection to Notice of Delay
Production Plan and prerequisite milestones
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Production Plan and prerequisite milestones Dear Sir, Following the ongoing coordination and discussions we had till date and based on your… Continue reading Production Plan and prerequisite milestones
RE – Notice To Restart The Production and Delivery of Pods For xxx- 4
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: RE – Notice To Restart The Production and Delivery of Pods For PDLM – 4 Reference: a) M/s xxx (Contractor Name)… Continue reading RE – Notice To Restart The Production and Delivery of Pods For xxx- 4
Notice of default (2)
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Notice of default (2) References: a) xxx dated 05 April xxxx b) xxx dated 19 April xxxx c) xxx… Continue reading Notice of default (2)
Notice of default.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Notice of default. References: a) xxx dated 05 April xxxx b) xxx dated 19 April xxxx c) xxx dated… Continue reading Notice of default.
Free Issue Materials status & Impact on production completion
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Free Issue Materials status & Impact on production completion Dear Mr. Wissam, We are writing to inform you that till date… Continue reading Free Issue Materials status & Impact on production completion