Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: RE – Notice to Restart the Production and Delivery of Pods for xxx – 4 Reference: a) M/s xxx (Contractor… Continue reading RE – Notice to Restart the Production and Delivery of Pods for xxx – 4
Instruction to stop production of pods
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Instruction to stop production of pods Reference: a) M/s xxx (Contractor Name) Letter xxx dated 12 December xxx b) M/s… Continue reading Instruction to stop production of pods
Instruction to stop production of pods
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Instruction to stop production of pods Reference: a) M/s xxx (Contractor Name) Letter xxx dated 12 December xxx Dear Sir, We… Continue reading Instruction to stop production of pods
Instruction to proceed with tiling works for the remaining 70 pods.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. S Subject : Instruction to proceed with tiling works for the remaining 70 pods. Dear Sir, Kindly note that in accordance with… Continue reading Instruction to proceed with tiling works for the remaining 70 pods.
Notice of delay in establishing the Letter of Credit
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Notice of delay in establishing the Letter of Credit Dear Sir, This is to notify the Main Contractor that he has… Continue reading Notice of delay in establishing the Letter of Credit
Request to expedite site preparation to allow for pods installation
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Request to expedite site preparation to allow for pods installation Dear Sir, We are writing to urge you to expedite the… Continue reading Request to expedite site preparation to allow for pods installation
Response to notice of delay in Engineering Works
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Response to notice of delay in Engineering Works Dear Sir, We are in receipt of your letter xxx dated 08… Continue reading Response to notice of delay in Engineering Works
Re-DELIVERY OF ALL PODS WITHOUT MARBLE
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Re-DELIVERY OF ALL PODS WITHOUT MARBLE Dear Sir, We are in receipt of your letter ref: xxx dated 05 December xxx… Continue reading Re-DELIVERY OF ALL PODS WITHOUT MARBLE
Updates on the delivery of tiles sanitary wares & accessories marble.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Updates on the delivery of tiles, sanitary wares & accessories, marble. References: a) xxx dated 21 June xxx b) xxx… Continue reading Updates on the delivery of tiles sanitary wares & accessories marble.
Response to Contractor’s allegations of delay
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : Response to Contractor’s allegations of delay References: a) xxx dated 21 June xxx b) xxx dated 06 July xxx … Continue reading Response to Contractor’s allegations of delay