Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E. xxx Attention : Ms. xxxx Technical Manager Project : xxx Qatar Subject : Missing Materials for Tower 2B Dear Sir, We refer to the above subject and would like to draw… Continue reading Missing Materials for Tower 2B
Missing & Damaged Materials for Tower 2B – Levels 1 to 14
Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E. xxx Attention : Ms. xxxx Technical Manager Project : xxx Qatar Subject : Missing & Damaged Materials for Tower 2B – Levels 1 to 14 Dear Keiran, We refer to the… Continue reading Missing & Damaged Materials for Tower 2B – Levels 1 to 14
Approved Shop Drawings
Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E. xxx Attention : Ms. xxxx Technical Manager Project : xxx Qatar Subject : Approved Shop Drawings Dear Ms. xxx, We refer to our email dated 6th September xxx in relation to… Continue reading Approved Shop Drawings
Quotation for Bulkhead Treatment at Townhouse – Rev. 1
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Quotation for Bulkhead Treatment at Townhouse – Rev. 1 Reference : Transmittal R8-1573 dated 2nd February 2016 Dear Sir, Further to… Continue reading Quotation for Bulkhead Treatment at Townhouse – Rev. 1
Release of Payment in Relation to the Kitchen Cabinet and Wardrobes
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Release of Payment in Relation to the Kitchen Cabinet and Wardrobes Dear Sir, We refer to our Subcontract Agreement with M/s… Continue reading Release of Payment in Relation to the Kitchen Cabinet and Wardrobes
Transmittal R8-1573 dated 2nd February xxx
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Quotation for Bulkhead Treatment at Townhouse Reference : Transmittal R8-1573 dated 2nd February xxx Dear Sir, Further to the reference above,… Continue reading Transmittal R8-1573 dated 2nd February xxx
Variations for Reception Counter – Additional Costs – Revision 1
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Variations for Reception Counter – Additional Costs – Revision 1 Dear Sir, Further to our letter reference xxx dated 17th November… Continue reading Variations for Reception Counter – Additional Costs – Revision 1
Site Delays
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Site Delays Dear Sir, Further to our Work Order reference xxx dated 23rd June xxx regarding the Interior Fit-Out Works for… Continue reading Site Delays
Variations Approvals
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Variations Approvals References: 1xxx dated 17th November xxx 2. xxx dated 7th September xxx Dear Sir, We refer to… Continue reading Variations Approvals
Variations for Reception Counter – Additional Costs
M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E. Tel: xxx Fax: xxx Attention : Engr. xxx Project Manager Project : (G+7F) xxx Apartment – Civil Works Subject : Variations for Reception Counter – Additional Costs Dear Sir, We refer to the recent requirements by the Client to change the… Continue reading Variations for Reception Counter – Additional Costs