Notification of delay

Notification of delay

Date                    : XXX

MCM Ref.           : XXX/P1010/AQQ/2021/01

To                         : XXX Air-Conditioning LLC.

XXX, [email protected]

Attention to     : Mr. XXX

Project               : Proposed G+1+R Villa for Mr. XXX, Dubai. On Plot No. XXX, Al Barsha Second, Dubai.

Subject               : Notification of delay

Dear Mr. Ahmed,

This is further to our continuous follow up since last six months and we do express serious concerned over failure of installation of copper tube, AC duct and delivery of AC outdoor units.

In tenure of project life, you have promised multiple times for several stage of works and failed repeatedly as usual to respect your own.

Please be informed, the delay penalty as per subcontractor agreement item F) under Article (1) will be imposed if you fail to complete your entire work by 5th September 2021.

Consider this is final warning and another opportunity from MCM to act you at site, fail to act at site as per said time frame may lead termination of subcontractor agreement and you will be sole responsible for that.

The additional cost will incur to completed the balance work will be charged to you with support of subcontractor agreement item H) under Article (1) and the same will be adjusted from your account with us.

Yours Sincerely

XXX LLC        

Leave a Reply

Your email address will not be published. Required fields are marked *