Notice of default in progress payment

Variation notification

Variation notification

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject:                Notice of default in progress payment

Dear Ms. Lian,

We are writing to put on record again that xxx is in blatant and flagrant default on Xxxx progress payments.  Your company has failed to certify and settle our progress payments as per our Sub-Contract Agreement payment terms.

  1. Our Interim Payment Application No. IPA-4 was due for payment on 26-Feb-xxxx and remains unsettled (please find attached copy of the certification).  The actual due date should be 12Feb-xxxx, but your certificate shows 26-Feb-xxxx.
    1. Default in payment is 69 days.
  2. Our Interim Payment Application No. IPA-5 was due for payment on 26-Mar-xxxx and remains unsettled (please find attached copy of the certification). The actual due date should be 14Mar-xxxx, but your certificate shows 26-Mar-xxxx.
    1. Default in payment is 40 days.
  3. Our Interim Payment Application No. IPA-6 was due for payment on 26-Apr-xxxx as per your certification and remains unsettled (please find attached copy of the certification).
    1. Default in payment is 9 days.
  4. Furthermore, our Interim Payment Application No. IPA-7 was submitted on 31-March-xxxx and remains uncertified till this date which is in breach of the terms of our Sub-Contract Agreement.

Your consistent and continuous default in settling our invoices is causing us serious cash flow issues.  Xxxx cannot continue financing your project without being paid.  Xxxx faced, and is increasingly facing difficulties paying its suppliers to source the necessary material for your project.

We urge you to settle all our overdue progress payments immediately. Xxxx will not be held liable for any impact the above may have on the delivery of pods or on any direct or indirect impact on site progress.

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       