Date: xxx
CC/269/SF/01
Kind Attn: M/s Strong Force
Project: 2B + G + 14 + Lower Roof Hotel Building
Plot No.: 373-1297 at Barsha, Dubai
Subject: Not to proceed for this project
Dear Sir,
With reference above, please do not proceed further regarding this project since there will be serious consequences with our existing contractor if we will replace.
As our project is already under severe delay the contractor and client have not agreed to replace for any new sub-contractor or for any change of anything in any regard.
So, we will look forward for our new project in Dubai land, we will proceed with Dubai land project.
Sorry for inconvenience if any.
Regards,
For xxx Contracting L.L.C
xxx
General Manager