Site Meeting

Site Meeting

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding Minutes of meeting no.69,  update for MEP , our concern  for other items and mock up room program

Dear Sir,

With reference to above, we have received the Minutes of meeting no.69 and kindly note the following:

  1. Item.4 mentioned in the minutes of meeting no.69, the note which you have mentioned for the nomination of the vanity counter, timber door and mirror issued ,please note that for the vanity counter ,no nomination has been issued yet . (Refer our letter ref no: CC/AP/274/16 DT.11.02.17)
  1. Water proofing variation work in toilet- it was instructed in the meeting as “not required”, kindly withdraw the formal instruction and record the verbal instruction.  

 b)  Contractor intimated that variation for the partition wall will be submitted and we will continue the work in 2nd floor .

c)Swimming pool pump room location verbally  confirmed in the meetings.