TABLE OF CONTENTS
- Scope / Objective
- Reference
- Access / Egress
- Health and Safety Hazards
- Safety Lighting
- Task Lighting
- Emergency Arrangements
- General
- Fire Precautions
- Communication
- Risks Control
- Hazards / Risks
- Control Measures / Permits
- 3rd Party Protection
- Environmental Considerations
- Definitions
- Responsibilities / Supervision
- Procedures / Method to be Employed
- Training
- Working Hours
- House Keeping
- Manpower Requirement & Supervision
- Material Requirement
- Plant & Equipment
- General
- Plant and Equipment Schedule
- Personnel Protective Equipment
- Power
- Working Platforms
- Q.C. Approvals and other Documentation
- Supporting Documentation
- Distribution
- Other Information
- Site Safety Engineers Approval
- Attachment – Sketches
1.0 Revision Status | |||||||
Revision No | Date | Prepared By | Reviewed By | Arabtech Approved | Revision Description | ||
0 | 15/11/04 | S.Georgiou C.Ctorides | G.Georghiou | M.Pickup | |||
1 | 15/12/04 | S.Georgiou C.Ctorides | G.Georghiou | M.Pickup | |||
2 | 20/03/05 | S.Georgiou C.Ctorides | G.Georghiou | M.Pickup | |||
1.0 SCOPE / OBJECTIVES
This Method Statement covers the installation of wall mounted Wiring Devices. This procedure is to define the method used to ensure that the wall mounted Wiring Devices have been installed as per the contract requirement.
- REFERENCES
- Particular Wiring Devices (Lighting) specification
Section 1105/SP/E-16141
2.2 Particular Wiring Devices (Small Power) specification
Section 1105/SP/E-16142
2.3 General Specification Requirements 16005,16010,16050
- ACCESS / EGRESS
Work will be carried out only when all associated works of Main Contractor been verified as completed.
4.0 HEALTH AND SAFETY HAZARDS.
Health and Safety procedure by Main Contractor and by A&P will be implemented for this job. The responsible Safety Officer as per A&P procedure will do a routine safety inspection.
- Safety Lighting.
Safety lights will be used in case of power failure ensuring the good illumination of the working area to aid evacuation if necessary.
- Task Lighting.
Adequate lighting will be provided ensuring the good illumination of the working area. Task lighting, where required will consist of tripod mounted fluorescent light.
- Emergency Arrangements.
- General: Site general safety procedures will be followed. In case of emergency the safety officer / foreman will stop the work, he will administer the emergency arrangements and he will report to assembly points as described during the Site Induction Course.
- Fire Precautions: No significant fire risks associated with this activity but general fire precaution measures will be taken as per Arabtec instructions to A&P.
- Communication: Communication from site areas to Site Office via mobile phones issued to senior foremen. In emergency situations the users of handheld 2-way radios to be notified if deemed that this can speed up notification of relevant personnel and/or the JBR01 Site Clinic.
- Risk and Controls.
- Relevant Risk Assessments (see Section 19 Attachments):
- WAH-001 Ladders and Step Ladders
- MAT-004 Disposal: Waste Materials
- PRT-007 Hand Tools
- PRT-010 Portable Electronic Equipment
- 3rd Party Protection: Applicable as per the contract only
- Environmental Considerations: After the finalization of the works the working area should be cleaned from any scrap materials on a daily basis related to the performed work.
5.0 DEFINITIONS
ATC – Arabtec Construction (LLC.)
A&P – A&P Paraskevaides and Partners LLC.
M.S. – Method Statements.
I.T.P – Inspection and Test Plant
6.0 RESPONSIBILITIES / SUPERVISION
- Project Manager – will have the overall responsibility of the Project for execution, quality and safety. Also he will maintain the planning progress and coordination of works with main contractor.
- Project Senior Electrical Engineer / Site Electrical Engineer – will be responsible for the day to day activities on site, for materials, drawings, testing & commissioning. The Project Senior Electrical Engineer will report to the Project Manager.
- Supervisor – will be directly responsible for the day-to-day job on site, for handling the technicians or any other staff assign to his area.
- Safety Officer – will be responsible for the Health and Safety aspects on site as per the Main Contractor and A&P Safety requirements.
- QA/QC Department – will be oversee all quality requirements and quality control measures for the Project in coordination with the Senior Electrical Engineer as outlined in the A&P QA Manual.
- PROCEDURES / METHOD TO BE EMPLOYED.
- Prepare and submit shop drawings for approval.
- Prepare and submit required materials for approval.
- Procure and deliver approved materials.
- Inspect materials upon arrival on site and ensure their good condition and specification compatibility.
- Offer materials for inspection to ATC/HYDER. Proceed if approved.(M.I.R)
- Ensure that conduits and boxes are clean and free of waste materials.
- Ensure that the installed back boxes are suitable for proposed wiring devices.
- Ensure that the back boxes are leveled and installed at the correct height.
- Ensure that the correct size, type and color of wires have been drawn in the conduits and ferruled accordingly.
- Identify from drawings appropriate type of wiring devices to be installed at each area.
- Bring from stores the correct type of wiring accessories and screws.
- Connect wires to the wiring devices.
- Make sure that the wires are connected correctly and secured.
- Fix wiring devices on the back boxes by using approved type of screws.
- Perform the polarity, circuit check as per test form of approved T&C procedure.
- Main Contractor should protect the device plates to prevent paint splatters during final coating / finishing.
- TRAINING
8.1 Tradesmen who will be used to perform the described work will be experienced electricians. If deemed necessary specific teams / individuals will undergo further training by the Production / Quality Assistance Departments.
- Toolbox talks will provide general training and awareness for each activity as well as in Health & Safety matters and precautions.
- WORKING HOURS
Normal working hours: 7.00 a.m to 5.00 pm
- HOUSE KEEPING
A&P personnel will clear work areas of scrap materials derived from their work on a daily basis ensuring a clean and healthy work environment and also to maintained free access and egress in the event of an emergency.
- MANPOWER REQUIREMENT & SUPERVISION
Installing the wiring accessories minimum requirement in manpower is one skilled electrician.
- MATERIAL REQUIRMENT
Material requirement for this activity are: Wiring Accessories, Screws.
- PLANT & EQUIPMENT REQUIREMENTS
- General: Screw drivers, Wire Strippers, Wire Cutters.
- Personnel Protective equipment: All personnel should wear at all time safety shoes, helmet and coverall, protective glasses and gloves.
- Power: Single-phase normal power where it is needed.
- Step Ladders.
- Testing Equipment.
- Q.C. APPROVAL AND OTHER DOCUMENTATION
- SUPPORTING DOCUMENTATION
- Shop drawings.
- Distribution Boards single line diagrams.
- Technical Submittal with Schedule of Wiring Devices.
- DISTRIBUTION
- Main Contractor,
- Senior Electrical Engineer
- Q.C. Engineer
- Site Electrical Engineer
- Tower Health & Safety Officer
- OTHER INFORMATION
Not applicable
- SITE SAFETY ENGINEER’S APPROVAL
Risk Mitigation measures as identified in the Risk Assessments in Section 19 to be inspected at regular intervals for Activity duration as identified in the Health & Safety Manual.
- ATTACHMENTS
- WAH-001 Ladders and Step Ladders
- MAT-004 Disposal: Waste Materials
- PRT-007 Hand Tools
- PRT-010 Portable Electronic Equipment