Method Statement Title: Testing and Commissioning of VFD’s.
1.0 Scope
1.1 This method statement details the Testing and Commissioning of VFD’s according to the specification section 15725.
Note: A separate method statement is submitted for installation of MCC’s and VFD’s. (Ref. ETA /MS/E-012)
2.0 Material
- All the materials shall be as per approved material submittals.
- Size and number of VFD’s shall be as per approved shop drawing and load schedule.
- Identifications and labels.
3.0 Applicable Location
3.1 VFD’s at East & West Podium Heat Exchanger Room.
4.0 Instruments.
4.1 Insulation Resistance tester (Megger) with Variable Voltage selections.
- Phase Sequence meter.
4.3 Multimeter.
Note : The calibration certificates of testing instruments shall be verified prior to usage and copies shall be included in the test reports.
- Test Procedure:
- Power Connection :
- Megger the incoming and outgoing power cable & connections for
Insulation check & short circuit. Please note that the power cables in the VFD’s terminals must be disconnected during this test or it may damage the VFD’s.
- Reconnect the cables and all power terminals shall be checked for tightness.
- All the power cables shall be supported well so that the stress is not on the terminals.
- All fuses and overloads shall be checked for correct sizes.
5.2 Control Connection :
- All control connection terminals shall be checked for tightness and continuity.
- The screens of the screened cables shall be checked for proper earthing.
- All terminations shall be cross checked with the drawing.
- Insulation Resistance Test using 500V Megger:
- Check the tightness of connections.
- Clean all the supporting insulators.
- Isolate the cables on incoming and outgoing side.
- Apply a megger voltage of 500Volts DC between Phases ‘R’ to earth for 1 min with Phase ‘Y’,’B’ & ‘N’ shorted and earthed and record the values.
- Similarly continue the test and record the values for the other phases.
- Pre-commissioning Test:
- Check the incoming voltage & phase sequence before switching ‘ON’ the incomer.
- Check control supply and stop lock provision and operation.
- Check bypass starter operation with the motor disconnected.
- Check VFD’s operation with the motor disconnected, from the control keypad.
- Set parameters as required and record the parameters.
- Check VFD’s operations from keypad after connecting the motor, also check motor’s direction or rotation.
- Check bypass starter operation with the motor connected, also check motor’s direction or rotation.
- Check external (remote) control of the VFD’s.
- Safety:
- Only experienced and skilled personnel shall be engaged for testing.
- Safety guards shall be in place and secured prior to start-up.
- Warning signs and tapes shall be placed during start-up and commissioning as required.
- All safety procedures shall be followed in accordance with the project health and safety plan.
- Safety officer shall check and ensure all safety precautions as followed.
- Records:
- Site Test Reports.
- Calibration certificates of testing instruments.
9.0 Reference:
- Specification Section 15725.
- Approved Drawings.
10.0 Enclosures:
10.1 Site Commissioning Report for VFD’s.