3-tips-for-Fire-Pump

Method Statement Title: Installation of Wet Riser Piping

Method Statement Title: Installation of Wet Riser Piping

Scope :

This method statement is applicable to the installation of Wet Riser Pipes and Hose reels, related fittings and accessories, to ensure that the pipe work and other related fittings and accessories are properly installed and conforms to the requirement of contract specification Section 15500 and NFPA 14.

2.0     Purpose :

To define the installation of Wet Riser Pipes with Mechanical Grooved and Threaded fittings, Fire fighting accessories e.g. Hose reel, Landing valve, etc.

3.0     Applicable locations:

  • East and West Towers and Podiums.

4.0     Method :

  • Preparation work

Before commencing any installation of Wet Riser Piping with fittings and accessories the following activities shall be carried out by the responsible representative of the company.

  • Check that the approved construction drawing of current revision is readily available for installation.
  • Verification of material used for installation, should have an approved material submittal.
  • Check the type and working conditions of pipe and applicable or required fittings and accessories as per the contract specifications.
  • Verify the availability of all required accessories on construction SITE prior to start of any installation activity.
  • Loading and unloading of pipes should be carried out by hands and use of skids should be avoided. Pipes should not be dragged along rough surface. Extra care should be exercised in handling small dia pipes to avoid damage.
  • Check the work area as per the safety aspect; it should be clean, tidy and safe for installation of fire fighting piping systems.
  • Installation Procedure
  • Mark out the location of hangers and supports for fire pipes and accessories as per the approved construction drawings.
  • Drill the marked position for the hangers and supports by using a drill of appropriate or required size.
  • Fix the flush anchor at drilled position by gentle and uniform hammering. During hammering use the “Setting Tool” of appropriate size for proper grip of the anchor in concrete.
  • Before fixing the threaded rod, insert a washer of appropriate size in to the rod.
  • Fix the threaded rod of appropriate dia and length into the anchor by twisting. For easy and balancing twisting of the rod use preferably two nuts locked together and a wring spanner for tightening.
  • Finally fix the washer near to the slab by tightening a nut over it; this will improve the strength and load bearing capacity of threaded rod and lock the support in place.
  • Measure length of pipe required, make due allowance of any pipe fittings to be used. Cut the pipe to the measured length in machine, ensuring that the ends are cut square. Flame cut ends will not be used for grooving.
  • For pipes more than 2 ½” dia grooved joints are required. With help of grooving machine prepare grooves at the pipe end to accept the Victaulic mechanical joints fittings as per the specifications and manufacturers recommendations.
  • For pipe less than 2 ½” dia, threaded joint is required, for this purpose, make external threads on the pipe’s end by using proper threading machine.
  • After making thread, these will be covered with jute. Wrap the jute around the entire length of the threads beginning with the second number thread from the end. Then screw the threaded end of the pipe in the adjacent fitting or pipe.
  • After preparing threads and the grooves, check them for their proper formation and depth.
  • The pipe will be checked for correct level and position and if necessary adjusted on the pipe support, or re-level the pipe with spirit level and tape.
  • For vertically installed pipes, install wall hangers at drilled position by adopting the same procedure. Install the pipes in the clips and “U” clamps. Provide additional support, to hang each landing valve.
  • Refer Annexure-I for a typical arrangement of landing valve.
  • Installation of Landing Valve
  • Mark out the location of landing valves on the pipes as per the approved construction drawing of current revision.
  • Provide mechanical Tee in the pipe to install the landing valve with the help of appropriate hole saw cutting machine prior to install the landing valve.
  • Install the “U” clamp fittings with each landing valve fitting.
  • Keep the canvas 2 ½” x 30 meter hose in the pre-installed metallic fire cabinet after the commissioning stage.
  • After completion of installation, remove burrs, dirt and construction debris and repair any damaged finishes including chips, scratches and abrasion. Make good paint finish.
  • After completion of installation work, work inspection request (WIR) shall be raised for Consultant’s inspection.
  • Hydrostatic test shall be performed as per attached format for the entire system to a pressure of 15 bars.

4.7       FIREX shall supervise the installation and testing and certify the same.

  • Equipment / Tools Required:
  • Electric drilling machine.
  • Mobile scaffold and step ladder.
  • Mechanical tool kit.
  • Measuring tape.
  • Water level.
  • Cutting tool.
  • Grinding machine.
  • Threading tool.
  • Grooving machine.
  • Safety
  • All safety regulations prevailing to this project site shall be strictly adhered to.
  • Ensure work area is clean and tidy.
  • Safety equipment (example hard hats, safety shoes, coverall gloves, goggles when necessary etc) to be worn all the times.
  • Ensure area is kept clear while lifting is in progress and cordon area off if necessary with warning tape.
  • Check all lifting equipment for visual sign of damage.
  • Check electric drill machine and extension leads for visual sign of damage.
  • Safety Officer shall check and ensure all safety measures are taken as required.
  • Attachment
  • Hydrostatic Test Certificate

Leave a Comment

Your email address will not be published. Required fields are marked *