1.0 Scope
This method statement details the method of installation of Lighting Fixtures as per Project Specification 16505.
Note
A separate Method Statement Ref. ETA/MS/E-40 shall be submitted for testing and commissioning of the Lighting Fixtures.
2.0 Material
- All materials shall be as per approved material submittals (schedule of materials attached herewith).
- Sizes of the wires shall be as per approved shop drawings / system manufacturers recommendation.
2.3 Type of luminaries shall be as per approved shop drawings.
3.0 Applicable Location
3.1 Tower E1,E2,E3 & W1,W2,W3, Podium areas and Villas.
4.0 Method
4.1 Storage
4.1.1 All materials received at site shall be inspected and ensured against approved material submittal.
4.1.2 Any discrepancies, damages etc. shall be notified immediately for further action.
4.1.3 Material found not suitable for the project are to be removed from site immediately.
4.1.6 Materials shall be stacked properly as per manufacturers recommendation and covered to prevent dust and water / moisture.
4.1.7 Manufacturer’s packing should not be removed till the time of installation.
4.1.9 Ambient condition of the storage place to be as per manufacturer’s recommendation.
4.2 Installation
4.2.1 Wiring to Light Fixtures. :
4.2.1.1 Ensure the relevant current / approved shop drawings are available with installation team.
4.2.1.2 Transfer the wire coils to the work place manually with the help of proper man power.
4.2.1.3 Check the colour and size of the wire is as per approved shop drawings.
4.2.1.4 Pull the wires manually through conduit installed as per approved shop drawings.
4.2.3 Lighting Fixtures. :
4.2.3.1 Ensure the relevant current / approved shop drawings are available with installation team.
4.2.3.2 Transfer the luminaries to the work place manually after checking the type of luminaire against relevant current / approved shop drawing.
4.2.3.3 Exact location of the luminaire to be marked at site as per approved reflected ceiling plan for ceiling (surface / recessed) installation.
4.2.3.4 Exact location and mounting height to be marked at site as per approved shop drawing for wall mounted installations.
4.2.3.5 For the luminaries which needs to be fixed on the false ceiling to be marked with exact dimension to make provision by false ceiling contractor.
4.2.3.6 Install the luminaire and terminate the wires properly.
4.2.3.7 Ensure the proper protection from damages during construction work.
4.2.5 Inspection request shall be raised for QC Verification and inspection of NMX and Consultant.
- Records. :
Inspection request duly signed-off by NMX and Consultant



