Method Statement Title: Installation of CCTV System

Method Statement Title: Installation of CCTV System

1.0       Scope

This method statement details the method of installation of CCTV System.

            Note

            A separate Method Statement Ref. ETA/MS/E- 0   shall be submitted for testing and commissioning of the Fire Alarm System.

2.0       Material

  • All materials shall be as per approved material submittals.
  • Type of cable shall be as per approved shop drawings / system manufacturers recommendation.

2.3       Type of Cameras shall be as per approved shop drawing.

3.0       Applicable Location

  • Tower E1, E2, E3, W1, W2, W3(Entrance Floor)

4.0       Method

4.1       Storage  

4.1.1    All materials received at site shall be inspected and ensured against approved material submittal.  

4.1.2    Any discrepancies, damages etc. shall be notified immediately for further action. 

4.1.3    Material found not suitable for the project are to be removed from site immediately.  

  • Co axial cables shall be stored with the factory packing on the flat surface.

4.1.5    Materials shall be stacked properly as per manufacturers recommendation and covered to prevent dust and water / moisture.

4.1.6    CCTV Equipment to be stored as per manufactures recommendation mentioned / marked in the packing.

4.1.8    Ambient condition of the storage place to be as per manufacturer’s recommendation.

            4.2       Installation

                        4.2.1    Co axial Cable

                                   4.2.1.1          Ensure the relevant current / approved shop drawings are available with installation team.    

                                   4.2.1.2          Transfer the cable to the work place with the help manpower..

                                   4.2.1.3          Check the cable drum for any external damage during transportation and ensure the type of cable against area of usage / application.

                                   4.2.1.4          Type  of the cable is as per approved shop drawings.

                                   4.2.1.5          In concealed application pull coaxial cable manually through conduit installed as per approved shop drawings and approved method statements.

                                   4.2.1.6          Leave enough length of cable at both ends of panel and devices for termination.

                                   4.2.1.7              No through joints is allowed without the sanction of the

                        Consultants.

.

                        4.2.2   CCTV EQUIPMENTS

                                   4.2.2.1             Ensure the relevant current / approved shop drawings are available with installation team.

  • Transfer the equipment to the work place with the help   

                        manpower.

                                   4.2.2.3              Location of the panel to be as per approved shop drawing after coordinating with other services.

                                   4.2.2.4             Fixing holes will be marked properly keeping back box of the panel in place.

                                   4.2.2.5             Fix back box properly and fix remaining panel accessories.

                        4.2.3   CCTV CAMERAS

                                   4.2.3.1             Ensure the relevant current / approved shop drawings are available with installation team.

                                   4.2.3.2             Exact location of the device to be as per approved reflected ceiling plan for surface / recessed installation

                                   4.2.3.3             For the Camera, which needs to be fixed on the false

                       ceiling, fix junction box of the camera above false

                       ceiling.                        

                                   4.2.3.4             Install the Camera  and terminate the cable properly.       

                        5.0      Records

            5.1       QC Installation Check List

            5.2       Inspection request duly signed-off by NMX and Consultant.

6.0       Attachment

6.1       QC installation check list formats for the following.

            a) Installation of  CCTV System

Leave a Reply

Your email address will not be published. Required fields are marked *