Project Name : Proposed Development of Residential Villa (G+2) On Plot No. xxx
Location : Palm Jumeirah, Dubai, United Arab Emirates
Client : Mr. xxx
Consultant : Al xxx Consultants
Contractor : M/S xxx Building Contracting LLC
METHOD STATEMENT FOR SHIFTING OF FOOTINGS
Table of Contents
1. Purpose
2. Tools Plant and Equipment
3. Procedure
1. Purpose
This method of statement describes the sequence and methods to be adopted for shifting of footings.
2. Tools
- Plate Compactor
- Measuring Tape
3. Procedure
Following are the below activities are inspected & rectified:-
1. Firstly, place the road-base & well compacted with plate compactor. (Inspected by Consultant)
2. Apply the spraying of Anti-termite solution. (Inspected by Consultant)
3. Placing of 1000 guage of polythene sheet. (Inspected by Consultant)
4. Placing the 100mm PCC concrete & extension of 500mm. (Inspected by Consultant)
Following are below activities are on hold waiting for approval:-
5. Application of two coats of Bitumen Primer and two layers of membrane sheet.
6. Placing of 5cm screed for protection of membrane.
7. Removal of previous footing shuttering & steel.
8. Remarking of new location as per latest Trakhees drawing.
9. Fixing the steel reinforcement & shuttering in new location as per Trakhees latest drawing.