METHOD STATEMENT FOR (PPR) Water Supply System
CONTENTS
CONTENTS………………………………………………………………………………………………………….
1.0 Scope……………………………………………………………………………………………………. 3
2.0 REFERENCES…………………………………………………………………………………………………………………………………………………………..3.
3.0 Responsibilities………………………………………………………………………………… 3
4.0 SEQUENCING………………………………………………………………………………………….. 3
5.0 CONSTRUCTION PROCEDURES……………………………………………………………… 4
6.0 TESTING………………………………………………………………………………………………… 5
7.0 EQUPMENT.………………………………………………………………………………………………………………………………………5
8.0 Materials……………………………………………………………………………………………. 5
9.0 Environmental Considerations…………………………………………………… 6
10.0 Attachments……………………………………………………………………………………… 6
Attachment 1: Key to Safety Symbols…………………………………………………………………………….. 7
This method statement describe the specific safe working method which will be use by Orasccom to carry out the Draining Piping System , it gives details of how the work will be carried out , what health and safety issues and controls are involved.
Project contract no. : Marassi project pkg # 75 & 76
Specifications : Technical specification Section 02510 & Section 221116.
- Construction Manager:
- Assigning tasks of responsibilities to senior site engineers.
- Monitoring adherence to project schedule.
- Expeding areas of concern to best achive project schedule.
- Senior Site Engineer:
- Assigning areas of responsibilities to site engineers.
- Site Engineers:
- Assigning areas of responsibilities to foreman.
- Continuous montoring of all aspects , and follow activates and co-ordinate with another activities due to any Damage of another works.
- Inspection of any installed Drainig pipes and fittings.
- Liasing with QC Engineers regarding works progression and availabilty for hold point inspections.
- Mechanical Quality Control Engineers:
- Ongoing inspection of all aspects of the installation works.
- Informaing consultant by works inspection request as and when his presence is required to carry out inspections.
- Follow the inspected works which approved by the consultant to prevent any damage and reported it by internal site instruction .
- Sequencing.
- Shop drawings approval.
- Material approval .
- Installation of pipes with its fittings .
- Testing according to the project specifications .
- :
5.1 Installation preparation
- .
5.2 jointing of (PP-R) pipes and fittings :
- Testing
- Backfill along the pipe except above the pipe joints and fitting untill we proceed with the pipe test.
- Test of the pipe according to the project specification section 02510 Division 3.5
- Subject systems to water pressure test to prove tigtness and to flow test to prove freedom from obstruction.
- Close all opening with plugs and fill system to point of overflow at highest opening.
- Vent all air and ensure that water reaches all parts of system to be tested.
- All close sections to be tested Hydrostatic pressure Test at least 15 minutes .
- Inspect all joints and pipes whilst under pressure and correct leaks or detective joints by replacing with new joints and materials .
- Use callibrate pressure gage for test to prove test pressure and continue use it at all test time.
- Repeat test after corrections are made and until systems are proven tight.
- Welding Device and tools .
- Plumber tool box.
- Personal tools.
Cosmoplast (PP-R) pipes and fitting. Transmittal No : PKG # 75&76- MT- PL-044 – Rev.01
- Considerations
All as per OCI procedures:
- HSEP 01 – Evaluation of Environmental Aspects
- HSEP 02 – Environmental Programme