METHOD STATEMENT FOR lighting fixtures Installation
- TABLE OF CONTENTS
1. SCOPE
2. definitions
3. HEALTH AND SAFETY
4. OPERATION
5. installation and fIXATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTs REQUIREMENTs
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1.SCOPE
- This procedure to clear the method of the supply, Installations of Lighting Fixtures .
- This document details Installation and Pulling of Lighting Fixtures :
- Preparation of work.
- Delivery and inspection upon arrival of material at site.
- Installation of the system.
2. definitions
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
- Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and use of the materials.
- Ensure all involved personnel shall be aware of the same.
- Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
- Material:
- Material used will be as approved by the Engineer.
- The sizes and routes routing will be as per the approved Shop Drawings.
- Storage and Protection:
- Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
- Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION and Fixation
- Pre-Installation:
- All materials and documentation relevant to this particular section of works will be checked and verified ensuring that these are correct and approved type.
- Prior to the commencement of works, ensure that the areas for permanent installation are ready, accessible and in suitable condition.
- Preparation:
- Engineer in-charge shall check to ensure that the Light Fixtures manufacturing, complies with specification and drawings.
- Engineer shall check to ensure that when installing Light Fixture in Hotel Guest Room, Corridor, Foyer, Front of House (FOH) and Back of House (BOH), architectural finishing work is completed.
- Ensure there is any physical obstruction during the delivery light fixtures.
- Ensure that the Light fixture design/equipment provided all are fully comply with the specification.
- Supplier shall deliver light fixtures unit to site and store it designated place.
- Handle the light fixture unit with care to avoid damage to components, frame and finish.
- When the light fixtures unit is received, unpack it sufficiently to inspect it fo
- concealed damage to determine that the shipment is complete and correct.
- If the light fixtures are to be stored prior to installation, replace the packing for protection during that period. When conditions permit, leave the packing intact until light fixtures unit are at their final installation location.
- Protect the fixtures against the dust and debris during construction period.
- A trolley or pallet may offer a more convenient method of handling the light fixtures to shift from one location to other.
- Installation:
- Site survey of the proposed light fixture is based on approved shopdrawing by foreman / sub-contractor together with Engineer.
- Installation must be carried out based on approved shop drawings & samples by foreman / sub-contractor.
- Most wall and ceiling fixtures–other than recessed fixtures–fit into standard electrical outlet boxes and are usually easy to mount.
- Most fixtures are mounted by a fixture stud or a fixture strap. Occasionally you need an extension nipple or a plain nipple for mounting certain fixtures.
- Any additional mounting devices required for special types of fixtures are usually included in the materials furnished by the manufacturer.
- Read and follow the manufacturer’s instructions carefully for a neat installation.
- Installation of Wall Fixtures:
- As a rule, you can install wall fixtures in regular outlet boxes with an ordinary strap and nipple.
- Different types of wall fixtures have different connecting arrangements, but you can usually attach the strap right to the fixture outlet box with screws. Then you can attach the wall fixture to the strap with a nipple and knurled cap.
- If the box has a central stud, you will need only an adapter and a nipple to attach the fixture. An adapter is screwed onto the stud, the nipple is attached to the adapter and the fixture is attached to the nipple
- Wall fixtures are usually quite simple to install. Manufacturers of wall fixtures design different mounting arrangements. The manufacturer will usually include complete installation instructions with the fixture.
- Installation of Ceiling Fixtures:
- Some ceiling outlet boxes have no stud in the center. In such cases, the ceiling fixture is usually installed with a strap that is screwed directly to the threads in the ceiling outlet box. The ceiling fixture is then attached to the strap with screws.
- The mounting arrangement illustrated will support most lightweight ceiling fixtures. Such an installation is simple, fast and meets most wiring codes.
- If the ceiling outlet box has a center fixture stud, mount the fixture by attaching the strap to the center stud with a locknut.
- Once the fixture strap is firmly attached to the fixture stud with the locknut,screw the fixture canopy to the strap with two screws.
- Heavier drop fixtures are often mounted with a hickey. This hickey screws to the center fixture stud.
- Attach a nipple to the lower section of the hickey with a locknut. Then mount the fixture canopy to the nipple with a collar.
- Hickey use in mounting drop fixtures varies according to the design and weight of the ceiling fixture. Almost all heavier drop fixtures require a hickey.
- Technical Assistance:
- The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
- This instruction shall be scheduled at the convenience of the staff.
- All such instruction shall be properly recorded.
- WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shopdrawings, approved specs and manufacturer recommendations.
6. RESPONSIBILITIES
Ø PROJECT MANAGER
- To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
- To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
- To ensure that all the equipment and material required executing the work are available according to the planned construction program.
- To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE ENGINEER
- To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
- To provide all necessary information and distribute responsibilities to his construction.
- To monitor the progress of work in relation with the work program and to report to the Project Manager.
- To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
- The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
- To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
- To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
- To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
- To control disposal of waste materials according to the instructions received from the site engineer.
- To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
- To inform the site engineer regarding areas ready for inspection.
- Foreman and the storekeeper are responsible for the distribution and control of materials.
Ø SAFETY ENGINEER
- Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
- Ensure all the implemented safety measures are adequate to maintain safe working on the site.
- Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
- Ensure that the site is maintained clean and tidy.
Ø TECHNICIAN FROM SUPPILER
- The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
Ø STORE KEEPER
- Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
- Charge hand and Experienced Technicians.
8. MATERIALS REQUIREMENTS
- Lighting Fixtures Components and Accessories.
9. EQUIPMENTs REQUIREMENTs
- The Equipment that will be engaged for Installation of Lighting Fixtures will be as follows:
- Screw drivers
- Hacksaw
- Needle nose pliers
- Electrical drill and drill bits (only for surface installation works)
- Diagonal-Cutting Pliers
- Wire Stripper/Cutter with Spring
- Side-Cutting Pliers
- Level
- Shank Screwdriver
- Electrical tape
- Voltage tester
- P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest )
10. WASTE MANAGEMENT
- The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
- The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
- Proper PPE must be worn at all time
- Permit to work at height > 2m where applicable
- Lifting operation permit (using crane) where applicable.
- Confined space permit where applicable.
- Approved work method statement and risk assessment will be made available to site.
- All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
- This method Statement should be read in conjunction with the below referenced documentations:
- ITP for Anti – termite Treatment.
- Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
- Copy of this method statement shall be issued to the following for information/ action/ comments:
- Project Manager
- Site Engineer
- Foremen
- Safety Engineer
- Technician From Supplier
- Store Keeper



