1.0 PURPOSE
- This method statement is applicable for the Installation of Water Booster Pumps for the project as mentioned in the Specifications & Approved Shop Drawings.
2.0 SCOPE
- This method Statement shall cover the Supply & Installation of Water Booster Pumps in line with project requirements as indicated in the Approved Shop Drawings & specifications.
3.1 Latest Approved shop drawings intended for the Water Booster Pumps
3.2 Specifications
- Project Quality Plan
- Project HSE Plan
- Material Approval.
4.0 DEFINITIONS
- PQP : Project Quality Plan
- PSP : Project Safety Plan
- HSE : Health, Safety and Environment
- MS : Method Statement
- ITP : Inspection Test Plan
- QA/QC : Quality Assurance / Quality Control Engineer.
- WIR : Inspection Request
- MIR : Material Inspection Request
- UPVC Class E : Ultra polyvinyl chloride
- UPVC : Ultra polyvinyl chloride
- HDPE : High density polyethylene
5.1 Project Manager
5.2 Construction Manager
5.3 Site Engineer
5.4 QA/QC Engineer (MEP):
5.6 Safety Officer
5.7 Store Keeper (SK)
6.0 EQUIPMENTS
Following tools shall be arranged before starting the job.
7.0 PROCEDURE
Ø Work Sequence/Procedure
- General Requirements
- All the materials received at site shall be as per the approved technical material submittal and Water Booster Pump set to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
- All construction/inspection/testing works shall be carried out in accordance with the specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
- Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.
7.2 Handling
7.2.1 Material Transport/ Delivery
- During transportation ensure that the equipment & its components (if any) are delivered in a shipping package and or shall be at least in a box covered with plastic. Extra care in unloading the equipment is required to avoid scratching or denting of finished surfaces of the Pumps & Frames.
- Where ever possible the loading and offloading of the Water Booster Pumps shall be carried out by hand.
- When required or necessary, forklift shall be used in unloading the materials.
- Equipment shall not be dropped onto hard surfaces & should not be dragged along the ground.
7.3 Storage
7.3.1 Storage on Site Store
- To ensure that deterioration of Water Booster Pumps does not occur during storage, it is recommended to store the pumps & its components in sheltered conditions that are protected from weather elements and accidental damage.
- Water Booster Pumps & its components shall be protected with plastic or cardboard and the area shall be barricaded with warning signs.
7.4 Sequence of Installation for Water Booster Pumps:
7.4.1 Safety
- All site safety rules & regulations shall be complied with.
- Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation, testing & commissioning and shall be recorded.
- All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.
- The persons using cleaning fluid and solvent cement have to wear hand gloves.
- Ensure that all operatives fully understand the method of these activities.
7.4.2 Pre- Installation Procedure
- Before commencement of installation activity, the supervisor must ensure that:
- Delivered Booster Pumps Set have been inspected & approved via MIR by the consultant prior to installation at site.
- Relevant documents or certificates shall be presented at the time of inspection if required by the Consultant.
- Permission to start or Civil Clearances prior to installation has been given by the main contractor.
- All relevant Shop drawings for the installation of Water Booster Pumps shall be available & approved by the consultant. No installation shall be done without Approved Shop Drawings.
- Installation activities shall only commence when all associated works by the Civil such as clearing of work place, construction of concrete plinth, water proofing, painting of walls/ floor etc. have been verified & completed.
- Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.
- Inspect the relevant area for any possible clashes with other services.
- Pumps shall be moved to the work area in a safe manner and shall not block access/ egress from the site with the help of a 3 ton pick- up and or a fork lift.
7.4.3 Installation Procedure
- Prior to installation, ensure that the data on the name plate matches with the required system data i.e. operating voltage, frequency & pump liquid temperature etc. MIR of the Water Booster Pumps should be approved by the Consultant.
- Prior to placing the Water Booster Pumps Set in concrete plinth, make sure that the anchoring bolts are matching with the Pump steel base anchoring hole alignment.
- Lay-out, marked & drill the location of the anchoring bolts on the concrete plinth.
- Each pump shall be mounted on a neoprene rubber pad concrete.
- Carefully place the Water Booster Pumps Set into the plinth. Check proper alignment and level by the use of a Torque Wrench.
- Place the nuts with one flat and lock washer, tight the nuts up to the required torque.
- After completion of setting-out of the Water Booster Pumps, lay-out and fabricate the suction & discharge piping and supports.
- Install the fabricated pipes and fittings along with the valves, flexible connectors & strainers as per the approved shop drawings.
- After completion of installation, raise an inspection request thru WIR to the Consultant for acceptance or Approval. Keep record for reference.
- Once installation has been accepted & approved by the Consultant, provide covering material to the Installed Water Booster Pump to avoid entry of dirt and dust. Remove all covers when termination of cables will start.
- Testing & Commissioning shall commence after final approval of the installation by the consultant.