CHECKLIST FOR INSTALLATION OF WATER BOOSTER PUMPS

Method Statement For Installation of Water Booster Pumps

CONTENTS

  1. 1.0 PURPOSE
  2. 2.0 SCOPE
  3. 3.0 REFERENCES
  4. 4.0 DEFINITIONS
  5. 5.0 RESPONSIBILITIES
  6. 6.0 EQUIPMENTS
  7. 7.0 PROCEDURE
  8. 8.0 ATTACHMENTS

 

 

 

1.0 PURPOSE

  • This method statement is applicable for the Installation of Water Booster Pumps for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

  • This method Statement shall cover the Supply & Installation of Water Booster Pumps in line with project requirements as indicated in the Approved Shop Drawings & specifications.

3.0 REFERENCE

      3.1  Latest Approved shop drawings intended for the Water Booster Pumps

            3.2  Specifications

  • Project Quality Plan
    • Project HSE Plan
    • Material Approval.       

4.0 DEFINITIONS

  • PQP                             : Project Quality Plan
  • PSP                              : Project Safety Plan
  • HSE                             : Health, Safety and Environment
  • MS                               : Method Statement
  • ITP                               : Inspection Test Plan
  • QA/QC                         : Quality Assurance / Quality Control Engineer.
  • WIR                             : Inspection Request
  • MIR                             : Material Inspection Request
  • UPVC Class E              : Ultra polyvinyl chloride
  • UPVC                          : Ultra polyvinyl chloride
  • HDPE                           : High density polyethylene

                                                                        5.0 RESPONSIBILITIES:

            5.1 Project Manager

5.2 Construction Manager

5.3 Site Engineer

5.4 QA/QC Engineer (MEP):

5.6 Safety Officer

            5.7 Store Keeper (SK)

6.0  EQUIPMENTS

Following tools shall be arranged before starting the job.

 

7.0   PROCEDURE

 

Ø  Work Sequence/Procedure

  •   General Requirements
  • All the materials received at site shall be as per the approved technical material submittal and Water Booster Pump set to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
  • All construction/inspection/testing works shall be carried out in accordance with the specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
  • Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.

            7.2        Handling

            7.2.1     Material Transport/ Delivery

  • During transportation ensure that the equipment & its components (if any) are delivered in a shipping package and or shall be at least in a box covered with plastic. Extra care in unloading the equipment is required to avoid scratching or denting of finished surfaces of the Pumps & Frames.
  • Where ever possible the loading and offloading of the Water Booster Pumps shall be carried out by hand.
  • When required or necessary, forklift shall be used in unloading the materials.
  • Equipment shall not be dropped onto hard surfaces & should not be dragged along the ground.

7.3        Storage

            7.3.1  Storage on Site Store

  • To ensure that deterioration of Water Booster Pumps does not occur during storage, it is recommended to store the pumps & its components in sheltered conditions that are protected from weather elements and accidental damage.
  • Water Booster Pumps & its components shall be protected with plastic or cardboard and the area shall be barricaded with warning signs.

            7.4 Sequence of Installation for Water Booster Pumps:

7.4.1 Safety

  • All site safety rules & regulations shall be complied with.
  • Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation, testing & commissioning and shall be recorded.
  • All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.
  • The persons using cleaning fluid and solvent cement have to wear hand gloves.
  • Ensure that all operatives fully understand the method of these activities.

7.4.2 Pre- Installation Procedure

  • Before commencement of installation activity, the supervisor must ensure that:
  • Delivered Booster Pumps Set have been inspected & approved via MIR by the consultant prior to installation at site.
  • Relevant documents or certificates shall be presented at the time of inspection if required by the Consultant.
  • Permission to start or Civil Clearances prior to installation has been given by the main contractor.
  • All relevant Shop drawings for the installation of Water Booster Pumps shall be available & approved by the consultant. No installation shall be done without Approved Shop Drawings.
  • Installation activities shall only commence when all associated works by the Civil such as clearing of work place, construction of concrete plinth, water proofing, painting of walls/ floor etc. have been verified & completed.
  • Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.
  • Inspect the relevant area for any possible clashes with other services.
  • Pumps shall be moved to the work area in a safe manner and shall not block access/ egress from the site with the help of a 3 ton pick- up and or a fork lift.

7.4.3 Installation Procedure

  • Prior to installation, ensure that the data on the name plate matches with the required system data i.e. operating voltage, frequency & pump liquid temperature etc. MIR of the Water Booster Pumps should be approved by the Consultant.
  • Prior to placing the Water Booster Pumps Set in concrete plinth, make sure that the anchoring bolts are matching with the Pump steel base anchoring hole alignment.
  • Lay-out, marked & drill the location of the anchoring bolts on the concrete plinth.
  • Each pump shall be mounted on a neoprene rubber pad concrete.
  • Carefully place the Water Booster Pumps Set into the plinth. Check proper alignment and level by the use of a Torque Wrench.
  • Place the nuts with one flat and lock washer, tight the nuts up to the required torque.
  • After completion of setting-out of the Water Booster Pumps, lay-out and fabricate the suction & discharge piping and supports.
  • Install the fabricated pipes and fittings along with the valves, flexible connectors & strainers as per the approved shop drawings.
  • After completion of installation, raise an inspection request thru WIR to the Consultant for acceptance or Approval. Keep record for reference.
  • Once installation has been accepted & approved by the Consultant, provide covering material to the Installed Water Booster Pump to avoid entry of dirt and dust. Remove all covers when termination of cables will start.
  • Testing & Commissioning shall commence after final approval of the installation by the consultant.