Mediahub GI boxes and Bathtub fittings still not supplied by employer.

Mediahub GI boxes and Bathtub fittings still not supplied by employer.

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject        :  Reminder Regarding Mediahub GI boxes and Bathtub fittings still not supplied by employer.

Dear Sir,

With reference to above, we would like to inform you that we donot have GI boxes for mediahub from 6th floor and above as well as we could not fix the bathtub in mock up room, as we do not have the fittings for overflow and outlet connection.

So, kindly note that we continuously following up for the electrical work under hold in partition wall from 6th floor and  mock up room bathtub not fixed yet because we are waiting the ba;ance fittings from the employer.

This is for your kind imformation, record and request to do needful.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager