Terms and Definitions
Client Supreme Committed for Delivery & Legacy
Contractor/Company DOMOPAN & INTEGRAL (JV) – The party, which has entered into
contract with Client for the execution of activities as mentioned in a
written agreement.
Engineer Supervision Engineer Consultant or his appointed representative
“Shall” Means a term which indicates that a provision is an absolute
requirement to be followed strictly in order to conform to this
document.
“Should” Means a term which indicates a provision is recommended.
Supplier / Vendor The party which entered into agreement with Client or contractor for
manufacturing, fabricating or supplying and any items for delivery to
Client or Contractor.
Third Party
Inspection
An independent party, which entered into agreement with Client or
contractor for ensuring that all activities are undertaken in
accordance with the requirements.
Imported Material Suitable material obtained from outside of the site
Hold Point Are mandatory notified verification points identified in the ITP
beyond which work may not proceed until verification and
acceptance has taken place by the relevant party. (QCS 2014 Section
2 Clause 1.1.3.7)
Witness Point Are notified verification points identified in the ITP where work may
proceed with or without verification and acceptance by the relevant
party. (QCS 2014 Section 2 Clause 1.1.3.18)
Surveillance Point Are verification points identified in the ITP attended on random
basis where work may proceed with or without verification and
acceptance by the relevant party. (QCS 2014 Section 2 Clause
1.1.3.17)
Record Review Point Are verification points identified in the ITP to review any result of
inspections or test reports to ensure it conforms to specified
requirements. (QCS 2014 Section 2 Clause1.1.3.16)
Page 5 of 62
Contents
Approval sheet…………………………………………………………………………………………….……2
Acronyms and abbreviations…………………………………………………………………….….……3
Terms and definitions…………………………………………………………………………….……….…4
1 Introduction………………………………………………………………….…………….…….….……7
1.1 Purpose ……………………………………………………………………………………………………7
1.2 Scope………………………………………………………………………………………………………..7
1.3 Required Permits ……………………………………………………………………………………….7
2 References……………………….………………………………………………………….…………..…7
2.1 Works Zone Traffic Management Plan (with New Road connected to Corniche)
2.2 Construction Phase Health and Safety Plan (SC‐DPP‐MDP‐PSL‐PLN‐HS‐00001)
2.3 DOMOPAN INTEGRAL (JV) Standard Procedure
2.4 Approved Material Submittals
2.5 Approved Shop Drawings
2.6 Approved Inspection Test Plan ITP
2.7 Project Specifications
2.8 QCS 2014 Section 21 – Part 17
2.9 NFPA 54,58
2.10 Woqood Requirements
2.11 Project Quality Plan
2.12 Fire Safety Standards issued by the Civil Defense Department (QCDD) – Ministry
of the Interior, Qatar
2.13 National Fire Protection Association (NFPA) Codes as applicable
3 Responsibilities………………………………………….……………………………….………..….…8
3.1 Senior Construction Manager………………………………………………………………..……………8
3.2 Construction Manager……………………………………………………………………..…….…….…….8
3.3 Site Engineer…………………………………………………………………………………………….………..8
3.4 Surveyor……..…………………………………………………………………………………………..……….…9
3.5 Site Supervisor / Foreman………………………………………………………………………..…………9
3.6 Health & Safety Manager…………………………………………………………………………..……….9
3.7 Health & Safety Engineer/Officer………………………………………………………………..………9
3.8 MEP Manager…………………………………………………..……………………………………….……..10
3.9 MEP Engineer………………………………..……………..…………………………………………..……..10
3.10 QA/QC Manger…………………………………………………………………………………………..…..10
3.11 QA/QC Engineer / Inspector……………………………………..…………………………………….10
3.12 Skilled labor………………………………………………………………………………………….…………11
3.13 Un‐Skilled labor………………….………………………………………………………………..…….……11
3.14 Operator…………………………………………………………………………………………..…………….11
3.15 Flagman…………………………………………………………………………………………..………..……11
3.16 Driver………………………………………………………………………………………..……………..…….12
Page 6 of 62
4 Resources (Manpower Tools and Equipment)….. ……..……………………..……….12
4.1 Materials…………………………………………………………………………………………….……….……12
4.2 Plant Tools and Equipment………………………………………………………………….…..……….12
4.3 Manpower………………………………………………………………………………………..…..…….……13
5 Health, Safety, Environmental Provisions………………………………….………………13
5.1 Health and Safety …………………………………………………………………………………….13
5.2 Environmental…………………………………..………………………………………………………………17
6 Procedure & Methodology of Work………………………………………………….………18
6.1 Material Handling…..…………………………………………………………………………………….….18
6.2 Material Storage and Inspection……………………………………………………………………….18
6.3 Site Planning and Preparation…………………………………………………………………………..18
6.4 Work Sequence and methodology….…………………………..……………………………………19
6.5 Installation Procedure For LPG System………………………………………………………..……19
6.6 Valve Regulator…………………………………………………………………..……………………………21
6.7 Installation of aboveground and Underground Pipe Network…………………………..23
6.8 Installation of Underground HDPE Pipe……….…………………………….……………..…..…25
6.9 Pipe Leak Test/Pressure test Description….………………………………………………………26
6.10 Electrical and Instruments Installation……………………………….…………………….…….27
6.11 Quality Control and Records……………………..………………..………………………..…..……31
7 Forms & Attachments ……………………………………………………………….……………..27
Document Number Title
Attachment 1 Inspection and Test Plan – Installation of LPG
system
Attachment 2 Inspection Request Format
Attachment 3 Risk Assessment – Installation of LPG system
Attachment 4 Environmental Risk Register– Installation of LPG
system
Page 7 of 62
1.0 Introduction
1.1 Purpose
The purpose of this Method Statement is to describe sequence of works involved in the
installation of LPG system in “Doha Port Re-Development Project- Combines Mina District &
Seawater Diving Pool Package” Project located at Doha. The works are based on project
specification and specific scope of works undertaken under the contractual obligations of the
contract.
This Method Statement will be followed and implemented by DOMOPAN /
STRUCTURE/UNIGAZ construction team.
1.2 Scope
The Scope covers the LPG system installation and hydrostatic testing activities involved in the
Installation & Hydrostatic Testing of LPG as per the Project Technical Specification. This
procedure is to fully define the installation and testing method and to ensure that the system
shall be installed and tested as per the contract documents.
Equipment piping, fitting and accessories will be installed as per WOQOD/QCDD standards &
as per approved drawing. The installation will be inspected and approved by a consultant –
“Doha Port Redevelopment Project – Combined Mina District & Seawater Diving Pool”, as
specified in the project specifications and drawings.
1.3 Required Permits
Before commencement of any works related to the task, permit must be secured from the
concern authorities. Following list of permits and licenses should be acquired:
• Project permits where applicable will be obtained and be in place prior to commencing
any site activity.
• Work at height Permit
• Hot Work Permits
• Shafts (Riser)
• Confined Spaces
• Leak/Pressure test permit
• Lifting Permit
• Equipment Permit
• Equipment License
2.0 References
2.1 Works Zone Traffic Management Plan (with New Road connected to Corniche)
2.2 Construction Phase Health and Safety Plan (SC‐DPP‐MDP‐PSL‐PLN‐HS‐00001)
2.3 DOMOPAN INTEGRAL (JV) Standard Procedure
2.4 Approved Material Submittals
2.5 Approved Shop Drawings
2.6 Approved Inspection Test Plan ITP
2.7 Project Specification.
Page 8 of 62
2.8 QCS 2014 – Section 21 Part 17
2.9 NFPA 54, 58.
2.10 WOQOD Requirements.
2.11 Project Quality Plan
2.12 Fire Safety Standards issued by the Civil Defense Department (QCDD) – Ministry
of the Interior, Qatar
2.13 National Fire Protection Association (NFPA) Codes as applicable
3 Responsibilities
3.1 Senior Construction Manager
• The Senior Construction Manager reporting to the Project Director, has overall
responsibility for the co‐ordination and implementation of the works including
Manpower, Plant, Equipment and Instruments Utilization, Engineering and all other
supporting Drawings.
• Responsible for the overall execution of the project. He will monitor all the activities with
his subordinates and make sure that the project is completed on time.
• Ensure that adequate worker’s welfare facilities and equipment are available to avoid
injury, health impairment or damage and to ensure providing quality works within the
planned timescale.
3.2 Construction Manager
• Carrying out the tasks identified by the Senior Construction Manager
• Complying with all Company Policies, Quality Procedures, Statutory Regulations and
project specifications.
• Ensuring that the Quality of material and installation of work is in accordance with the
acceptance criteria identified for the project.
• Ensuring that the work is completed in accordance with the specified QA / QC system &
in a Safe manner.
• Monitoring all Sub Contractors work closely to ensure that the Quality of the work is as
per specification and is completed on time.
• Review of short‐term planning & advising the Senior Construction Manager on any
problem areas.
• Completing all necessary documentation to be included in weekly & monthly reports.
• Issuing instructions to the Engineers, Supervisors and others to complete the work in
accordance with the project program.
• Co‐ordination with the Logistics / Plant Manager for any equipment or plant required.
• Completing all Daily Reports on time & ensuring that the information is 100% correct.
3.3 Site Engineer
• Site Engineer reporting to the Senior Construction Manager for all the activities at site.
• Assigning task / activities to supervisor.
• Ensuring the execution of tasks within the allocated time frame.
• Ensure that work is carried out as per approved shop drawings
• Ensure that work is carried out as per the submitted method statements
• Monitor for usage of correct and quality materials.
Page 9 of 62
• Monitoring and controlling execution with respect to time and quality.
• Expediting areas of concern to achieve work activity time frame in coordination with
other discipline engineers.
• Liaising with QC Engineers regarding work progress and hold point inspection.
• Ensuring the work is carried out as per approved Method Statement.
• Ensuring usage of correct and approved materials.
• Ensure the safety and welfare of all labors.
3.4 Surveyor
• Chief Surveyor reporting to the Senior Construction Manager.
• Use appropriate equipment to complete assigned task.
• Keep accurate notes and records to describe and certify work performance.
• Abide by all site Quality & HSE Requirement.
• Determine methods to establish survey control points
• Ensure that survey points are properly maintained,
• Surveying and setting out as per drawing.
• Ensure that the required surveys are planned and performed in accordance with this
document.
• Will ensure the calibration of equipment.
3.5 Site Supervisor / Foreman
• Assigning works to technicians / workers.
• Ensuring the execution of tasks within the allocated time frame.
• Monitoring and controlling execution with respect to correctness, time and quality.
• Expediting areas of concern to achieve work activity time frame.
• Liaising with Site Engineer regarding work front availability, work progress and readiness
for inspection of the installation.
3.6 Health and Safety Manager
• Shall advise DOMOPAN INTEGRAL (JV) staff and management on ways to fulfill the Health
and Safety requirements mentioned in the Health and Safety Plan.
• Shall support the Site Safety Representatives on health and safety related issues.
• Carries out Health & Safety Hazard Impact / Risk Assessment for the site.
• Carries out work place inspections and raises Health & Safety NCR’s for Nonconformities.
• Ensures work site is in safe conditions
• Ensures calibration & approval of all Health and safety monitoring Equipment and ensure
needed certifications for lifting equipment, machineries, Slings etc.
• Facilitates implementation of corrective & preventive actions identified as part of Health
and Safety Inspections and Audits.
• Ensures First aid and Health and Safety Emergency Procedures for the site are
established and maintained.
3.7 Health & Safety Engineer/Officer
• Safety Officer reporting to Senior Construction Manager for all the activities at site and
he will report to the Project / Safety Manager and will be fully responsible for Health
Page 10 of 62
and Safety requirements of the project. He will be conducting all required Tool Box Talk,
Safety reports and make sure, that all the safety procedures are met at site.
• Ensure that required Personal Protective Equipment (PPE) is always worn.
• Ensure all workers / technicians are briefed about hazards associated with their type of
works.
• Highlights hazards associated to each work activity.
• Close monitoring of workers and worksite for any safety related issues.
3.8 MEP Manager
• MEP Manager will be responsible all the MEP related works in the project.
• He will be mainly responsible for selecting and evaluating MEP Contractor for the project.
• He will be responsible for all the MEP Design & Drawings submission & approval.
• He will be responsible for monitoring MEP Contractors works and conducting meetings
with MEP Contractors.
• He will be responsible for reviewing all the material submittals / shop drawings/ Testing
& commissioning procedures submitted by MEP Contractor.
3.9 MEP Engineer
• Review the shop drawings supplied by sub‐contractors.
• Monitoring the MEP Contractors work.
• Coordinating with MEP Contractor & Client/Consultant.
• Monitoring MEP Testing & Commissioning works and review Commissioning reports.
• MEP Engineer will be responsible for LOTO System implementation.
• Follow the Quality, Safety and Environmental management requirements in his area of
applications.
3.10 QA / QC Manager
• Shall advise DOMOPAN INTEGRAL (JV) staff and management on ways to fulfill the
Quality requirements mentioned in the Project Quality Plan.
• Shall prepare and develop a process of monitoring the procedure mentioned in this
document to insure it is strictly followed and will continue to evaluate its effectiveness
and revised as necessary for quality improvement.
• Shall conduct an awareness training to personnel directly involves imparting a proper
understanding of its requirements
• He shall support the QA/QC Engineer on quality issues in the site.
3.11 QC Engineer/Inspector
• Will carry out the material inspection to ensure that materials are approved, and they
meet the desired quality standard upon receipt
• Assign areas of responsibilities and request approved 3rd Party Technicians.
• Ensuring that the project Inspection and Test Plan (ITP) is briefed to and are being
followed by the construction team.
• Ensures required quality documentation is fulfilled and approved.
• Initiating and maintaining check sheets / records for works.
• Liaising with Site Engineer regarding work progress and hold point inspection.
• Performing hold point inspection of finished parts.
• Expediting areas of concern to best achieve project quality requirements.
Page 11 of 62
• Real time monitoring of on‐going work activities.
• Status reporting of work progress and readiness for inspection.
3.12 Skilled labor
• Carry out their work in such a way, that they do not create for themselves or any other
person risk to health and safety, and do not impact the environment to the maximum
extent possible or affect the quality of work.
• Will be suitably trained, experienced and skillful for the assigned work.
• Will wear suitable PPE and perform the work in a safe manner as educated through TBT.
• Will be accountable to their Trade Foreman and work under his direct instructions.
3.13 Un‐Skilled labor
• Carry out their work in such a way that they do not create for themselves or any other
person risk to health and safety, and do not impact the environment to the maximum
extent possible or affect the quality of work.
• Unskilled labor will work under the skilled labor in supervision of Foreman / Supervisor.
• Will wear suitable PPE and perform the work in a safe manner as educated through TBT.
• Will be accountable to their trade Foreman and work under his direct instructions.
3.14 Operator
• Carry out their work in such a way that they do not create for themselves or any other
person risk to health and safety, and do not impact the environment to the maximum
extent possible or affect the quality of work.
• Operator will work under the supervision of Foreman / Supervisor.
• Heavy Licensed Operator Drive and control the construction equipment.
• Maintain proper coordination and cooperation with the road and transport system while
driving/working.
• Will wear suitable PPE and perform the work in a safe manner as educated through TBT.
• Will be accountable to their trade Foreman and work under his direct instructions.
3.15 Flagman
• Carry out their work in such a way that they do not create for themselves or any other
person risk to health and safety, and do not impact the environment to the maximum
extent possible or affect the quality of work.
• Flagman will work under the Operator in supervision of Foreman / Supervisor.
• Flagman guides traffic in a construction zone.
• Use signal flags to work with the traffic patterns and ensure the safety of other
construction works.
• Will wear suitable PPE and perform the work in a safe manner as educated through TBT.
• Will be accountable to their trade Foreman and work under his direct instructions.
Page 12 of 62
3.16 Driver
• Carry out their work in such a way that they do not create for themselves or any other
person risk to health and safety, and do not impact the environment to the maximum
extent possible or affect the quality of work.
• Driver will work under the supervision of Foreman / Supervisor.
• Licensed Driver Maintain, drive and control the construction vehicle.
• Will wear suitable PPE and perform the work in a safe manner as educated through TBT.
• Will be accountable to their trade Foreman and work under his direct instructions.
4 Resources (Manpower, Tools & Equipment)
4.1 Materials
The following materials are required for the execution of the work.
• LPG Storage main tank.
• Vaporizers
• Valves, Regulators.
• Gas Leak Detection panels and sensors and its accessories
• Valves
• LPG system piping network
• LPG Paint- 3 Coating
4.2 Plant Tools and Equipment
• Mobile crane
• Lifting tools & gears
• Chain Hoist
• Eye Bolt / Tie hook
• Drilling Machine.
• Measuring Tape
• Sprit level
• Hand Tools
• Pipe Fitters Tool Box.
• Helper’s Tool Box
• Electrician Tool Box
• Threading machine
• Grinding machine
• Welding Machine
• Voltmeter, Ammeter, Megger
• Pressure Gauges
• Plug stop end caps for pipes
• Nitrogen Cylinder(s).
• Grinding / Cutting machine(s).
• Manual operated fork lift.
4.3 Manpower
• Sr. Construction Manager
• Site Mechanical Engineer
Page 13 of 62
• Site Electrical Engineer
• Foreman/Tradesmen
• Pipe fabricator / Fitter
• Electrician
• Traffic Engineer
• Welders
• Surveyor
• Foreman / Supervisor
• Safety Officer
• Skilled Labors
• Riggers
• Unskilled Labors
• Driver
• Skilled Labor
5 Health, Safety, Environmental Provisions
5.1 Health and Safety
SQW collaborate with DOMOPAN INTEGRAL (JV) committed to provide a comprehensive
Occupational Health and Safety Oriented and Lost Time Injury (LTI) free for all the
workplaces in the construction sites. Please refer to Health and Safety Plans for more details.
5.1.1 General Health and Safety Policy
a. Daily Pre‐Job briefing shall be held at site. Pre‐Job briefing blank form enclosed in
Annexures.
b. Work specific training will be given to the workers. All workmen will be informed about the
nature and hazard involved in the complete scope of the job.
c. Emergency Drills will be conducted to test preparedness and response within every six
months in line with DOMOPAN INTEGRAL (JV) emergency procedure
d. Operators of mechanical machinery shall be certified for the equipment and vehicles they
operate and must always have in their possession Qatari Driving License for the class of
vehicle and the required Third‐party competency certificate.
e. Operators of mechanical machinery shall be subject to medical examination.
f. The outcome of the risk assessment shall be communicated to the workforce in the form
of a Tool Box Talk to be held at the start of the works and at the start of each shift or
when for any reason the task has been suspended, before work resumes.
g. SQW shall provide adequate assistance for client / consultant / Main contractor
representative during inspection.
5.1.2 Risks
Page 14 of 62
a. Hazard identification and risk assessment has been carried out and some of the identified
hazards are detailed in the attached Hazard Identification and Risk Assessment.
b. SQW shall follow DOMOPAN INTEGRAL (JV) established, implemented and maintained an ongoing
identification of hazards, assessment of their risk and determining the necessary
controls. The records are kept up‐to‐date and being reviewed periodically.
c. Job safety analysis shall be done to integrate accepted safety and health principles and
practices into a job or task. Each job or task will be analyzed by breaking them down into
distinct steps to identify the hazards and precautions and implemented with the aim of
ensuring a safe job execution.
5.1.3 Health
a. Sanitary Facilities
• All basic sanitary facilities will be available on site.
b. Health Care Facilities
• DOMOPAN INTEGRAL (JV) shall provide the number of First aid boxes furnished with the
medicines, tools and equipment. The First Aid box shall be available in offices of Clients,
DOMOPAN INTEGRAL (JV), Satellite and rest shelters depending on number of
employees.
• A first‐aider shall be provided for every 25 workers.
• DOMOPAN INTEGRAL (JV) shall appoint a full‐time medical nurse at site in addition to the
first‐aid box.
5.1.4 Safety
a. Induction
• SQW shall maintained provided sustainability awareness thru Induction & Training of all
personnel prior to discharging them of their duties and responsibilities in the site by
DOMOPAN INTEGRAL (JV).
b. Anticipated Risks
• Suspended load
• Slip, trip & fall
• Equipment failure
• Defective tools & equipment
• Pinch point
• Fall from height
• Dropping object
• Dust
• Flying particles
• Fumes
• Fire
Page 15 of 62
• Electrocution
c. Permits and Certification
The following work permits, and certificates shall be available in the work area as required:
• Work at height Permit;
• Lifting permit;
• Leak test permit;
• Valid registration, 3rd Party certificates & insurance for heavy equipment (if any).
• Valid licenses and insurances for operators
d. Inspections
• Heavy equipment shall have third party certifications and shall be regularly inspected with
the approved required daily checklist to ensure high quality standards and efficient
equipment is being used.
e. Personal Protective Equipment (PPE)
Some appropriate PPE shall be worn as per the work required but not limited to;
• Safety helmet
• Safety Goggles
• Safety Boots
• Hand gloves, Respiratory Mask,
• Full body harness (Work at heights) (if any)
f. Traffic Plan and regulation
• SQW shall comply with DOMOPAN INTEGRAL (JV) Traffic Diversion Plan (TDP) detailing
the required number of equipment, planning of the works, layout of the access road,
required road signage and to strictly adhere as such;
• A trained Flagman and Banksman will be available as required;
g. Subcontractors
SQW subcontractors shall be inducted and obliged to follow all the health & safety
rules regulations being implemented on the site. All SQW Health and Safety measures
shall be applied the same to the subcontractors in line with DOMOPAN INTEGRAL (JV)
h. Information dissemination
Health and safety knowledge shall be disseminated and cascaded from top management to
the ordinary workers through;
Site Induction
Safety Toolbox talk
Bulletin Boards
Training Courses
Page 16 of 62
Group Discussions
Site Instructions
Engineers, Supervisors & Foreman
i. Site Night Works (if any)
Working shall be prohibited not unless otherwise it is deemed necessary with reasons.
In the night shift will be arranged with all the necessary Safety and Health facilities. Site
representative for supervision will be available and Client approval will be secured for
working night.
SQW shall coordinate with M/s DOMOPAN INTEGRAL (JV) to provide lighting to avoid
visual fatigue and prevent glare and reflection into person’s eyes.
During night operations, only clear or amber colored safety glasses shall be worn.
Contact lenses can be worn with eye protection except while using a respirator.
Any general lighting source shall be mounted at a height enough to keep it well above
the line of normal vision.
Any local lighting source shall be mounted and arranged to confine the light to the
immediate area to be illuminated.
Barricade the Hazardous area and use flashing lights.
Keep combustible materials away from lights.
Personnel to wear high visibility reflective vest.
j. Emergency Response
SQW shall follow DOMOPAN INTEGRAL (JV) Contingency Plan and Emergency
Procedure during the period of the work and shall ensure that their staffs are fully
familiar with the emergency procedures, use and location of the essential emergency
equipment, such as breathing apparatus, fire extinguishers, fire hoses etc.
Safe assembly point (Muster Point) is in near entrance of each site Location;
In case of emergency, the work force will assemble in the safe assembly point in
consideration the wind direction (Safe assembly point is provided with sign boards);
Time keeper / Security Personnel shall carry the attendance register of specific location
for head counting of attendees;
Safety Officer shall verify the attendance register to ensure that all the personnel have
evacuated from the hazard area;
Attempt to put out the fire / rescue operation shall be made only when it is safe to do
so. Fire shall be put out under supervision of trained personnel.
All flammable material in the vicinity of fire shall be removed;
Safety Engineer / Safety Officer shall call Fire Brigade, Ambulance, Police, etc., & Contact Sr.
Construction Manager / Health Safety Manager for further action;
First aid shall be administered to the injured personnel, if any;
Project Manager shall ascertain the risks and ensure control measures are
implemented prior to resuming work.
Page 17 of 62
EMERGENCY TELEPHONE NUMBER
DOMOPAN INTEGRAL (JV) EMERGENCY 30931387
POLICE, CIVIL DEFENSE AND EMERGENCY 999
WATER AND ELECTRICITY EMERGENCY 991
ACCIDENTS AND EMERGENCY – HAMAD
HOSPITAL
(+974) 4439 2111
TELEPHONE DIRECTORY 180
EMERGENCY CONTACT PERSON AND NUMBER
MR. NABIL ELMASRY – Sr. CONSTRUCTION
MANAGER
55869878
MR. KAMEL – PROJECT MANAGER (SQW) 31001121
MR. HAMID RAZA – SAFETY MANAGER 30204171
MR. TURAB HAYDER – SAFETY MANAGER (SQW) 66584526
MR. ASHISH KUMAR – WELFARE MANAGER 33520021
NISHADU ISMAIL – H & S OFFICER 31116476
5.2 Environmental
SQW is committed to be environmentally friendly and to prevent pollution by reducing the
impact of its activities, products and service on the environment in line with DOMOPAN (JV)
- Vehicle/Equipment maintenance will only be done in designated area (Maintenance
Workshop) - Environmental Emergency arrangement. i.e. Provision of Spill Kits
- All waste resulting from this activity will be properly managed and segregated. i.e.
Segregation Non‐hazardous waste for adequate disposal by a license waste carrier - All waste resulting from this operation will be properly managed as per Waste
management Plan in Construction Environmental Management Plan, submittal no. SCDPP‐
MDP‐DPQ‐PLN ‐EN‐00006 - Any hazardous materials that maybe used during this operation shall be appropriately
stored as per the MSDS. - MSDS for all substances used will be available at the designated storage area and
where they are being used - Waste Management‐ All the waste produced shall be segregated, based on its
availability/ practicability for recycling/ reuse. Hazardous materials and waste like
paints. Thinners, etc. shall be segregated from the non‐hazardous materials. - Noise Emissions‐ Elevated levels of Noise, generated during the task stage shall be
minimized and the personnel involve in the task shall be protected with ear plug/ muffs
as required.
Page 18 of 62
6 Procedure & Methodology of Work
6.1 Material Handling.
• Ensure that all the materials received to the site are according to the approved material
submittal.
• Materials will be transported to the site in accordance with the manufacturer’s
recommendation so as to avoid damage or deterioration.
• Care must be taken to ensure the materials are evenly supported throughout during
transportation.
• Supports must be free from sharp edges to prevent damage to the unit during
transportation.
• Pipes, Panels and accessories shall be offloaded in the site store.
• The Tanks shall be offloaded from the vehicle by using a forklift/crane. Equipment for
handling the tank shall be of adequate size to lift and position the tank. Tanks shall be
carefully handled using cables of adequate length and size. Attach to the tank using the
lifting lugs provided. Care should be taken that the angle between the two cables, at the
lift point, shall be no greater than 60 degrees.
• Collect the relevant document from the supplier.
• Unload the Vaporizers as per manufacturer/ Supplier recommendation.
• Store the Vaporizer’s as per manufacturer/ Supplier recommendation.
• Collect all accessories as per delivery note. If found any missing immediately inform to
the site engineer
• Valves and gauge are covered in the storage area
• All materials shall be offloaded in a designated lay down area. LPG Tanks shall be
offloaded in a proper flat storage area and later shifted wherein to be installed in Below
Grade.
• Ensure timber supports on all equipment and materials during storage. End caps or
coverings shall be in place until installation for pipes and tank openings.
• Materials should not be dropped into hard surfaces and should not be dragged along
the ground.
• Tank Handling: Tanks shall be handled and installed by Unigaz.
6.2 Material Storage and Inspection.
• All packages for the LPG System reaching site shall be identified as per the packing list
• The LPG System parts will be stored in a clean/dry place. Parts to be covered by
polythene sheets.
• Materials received at the site shall be inspected to ensure that the materials are as per
approved material submittal in terms of their make, model, type country of origin and
capacity.
• Any discrepancies, damages etc., found will be notified and reported for further action.
• Store the pump as per manufacturer/supplier recommendation.
6.3 Site Planning and Preparation.
• All approved/shop drawing shall be kept at the site to the respective Site supervisor.
• All areas including the trailer/crane movement places shall be barricaded with required
signaling tape and sufficient signage to be provided towards safety warning.
Page 19 of 62
• Sufficient illuminations shall be provided in case the work is being carried during night
time.
• Level and finish of foundation to be checked as per approved shop drawing and
manufacturer’s recommendations.
• Finishing of foundation to be inspected and approved by general inspection.
• Works shall not start until an approved construction drawing is issued. UNIGAZ shall
ensure to obtain necessary approvals on time to avoid delay.
• Work will be carried out only when all associated works have been verified for
completion. Safe access to work areas shall be provided. Local access equipment
(tower, scaffolds etc.) shall be provided and approved by a competent person prior to
the commencement of works.
• Materials shall be moved to the work area in a safe manner and shall not block
access/egress from the site. Suitable mechanical aids shall be used where Diesel Fuel
Tanks to be moved or lifted into position. Such equipment shall be planned for in
advance of works.
• LPG Tank and other related accessories will be stored at a dry location in the laydown
area. They will be protected and covered by polyethene sheeting.
• Where high-risk works are involved (heavy lifting operations, work in confined spaces)
then a Safety Method Statement shall be developed in accordance with HSE
procedures.
• Before installations, it is ensured to inspect the Vault.
• Ensure that all drawings are current and marked “Approved for Construction”. All shop
and Approved for Construction drawings shall be certified by the specialist.
• Inspect the relevant area for any possible clashes with other services.
• Before any materials are installed it will be ensured that these have been inspected at
the site and have been approved as per the relevant Material Delivered to site form
(MDS).
• Inspect all materials and verify that they are undamaged and suitable for the relevant
application.
• The Tanks should be grounded as per WOQOD/QCDD requirements. Anode rods or
anode bags connected through cables can be used for grounding purposes.
• Where the tank body is in contact with the earth or foundation, it should be protected
from external corrosion through grounding.
• Aboveground tanks should not be located above underground utilities or directly
beneath overhead power lines.
• All packages for the LPG System reaching site shall be identified as per the packing list
• The LPGl System parts will be stored in a clean/dry place. Parts to be covered by
polythene sheets.
6.4 Work Sequence and Methodology
• Check all material delivered to the site is inspected properly by QA/QC Engineer and
check if it is stored properly.
• MIR shall be raised for the inspection of insulation materials, to the Consultant
Engineer.
• Work shall be carried out by the site staff under strict supervision and guidance of the
concerned Supervisors / Foremen / Engineers.
6.5 Installation Procedure for LPG System
(A) Bulk Tank Storage Tank Installation.
Page 20 of 62
• The tanks area should be ready for off-loading and installation of the tanks as follow: –
There should not be any electrical plants or installations in the vicinity because they
may generate stray currents (e.g. electric lines).
• Assess the area for positioning of the crane for installation of LPG tank.
• Check ground level of tanks foundation. Install the tanks inside the foundation and fixing
them with anchor bolts.
• Start sand filling with sieved sand around the tanks up to 50% of the tanks level and
spray water. The markings will be done by Unigaz.
• Install catholic protection to protect the Underground tank from corrosion by making it
as a cathode. To make tank a cathode, you have to attach an anode to it. Both have to
be in an electrolyte such as earth or water. Install an anode consisting of magnesium
metal packed inside a cloth bag containing of conductive material and earth backfill with
a wire that is attached to the magnesium and to the tank
• Continue filling with sand with courteously compacted to prevent excessive shrinkage,
till the specified marks on the tanks, keeping the last layer 10cm of gravels
• Once the backfilling completed install all the tank valve accessories like vapor
inlet/outlet, liquid inlet/outlet safety relief valves, pressure gauges, High level and low
level indication, Excess flow check operations are built-in within the tanks supplied by
WOQOD.
TANK ANCHORING
TANK FITTINGS BACKFILLING OF TANKS
Page 21 of 62
(B) Vaporizer Installation
• The vaporizer must be firmly fixed on the solid stand or concrete foundation.
• Leave enough space around the vaporizer for easy access for overhaul inspection and
maintenance.
• Execute the piping works properly in conformity with approved drawings in order to
connect the vaporizer to the gas tanks.
• The vaporizers are protected from over pressure.
Connect electric cables according to the capacity of each device, cable with suitable
thickness and length must be prepared as per below:
a. All connection will be through junction box for each device.
b. All cables have to be joined with terminal block threw a junction box.
c. Suitable data cable will be used to connect each instrumentation device
(level indicator, pressure, temperature sensors).
6.6 Valves Regulators
(A) Regulators.
• General: All regulators shall be designed, installed or protected so their operation will
not be affected by the elements.
First stage regulator: Single stage suitable for LPG service.
a. The regulators will reduce the pressure from tanks pressure (4 Bar) to max
network pressure (1.2 Bar).
b. A stand by regulator will be installed in case any break down
• Second stage regulator: Single stage suitable for LPG system.
The regulator will reduce the pressure from main network pressure to the required
pressure for kitchens.
VAPORIZER UNIT
REGULATOR
Page 22 of 62
(B) Pressure Gauges.
• General: All Pressure gauges shall be installed as per the approved P&ID.
• Pressure gauges are installed to show the reading of the inlet/outlet pressures for pipe
and the range should be 4 times of the maximum working pressure
• Will be threaded up to 2’’ size.
(C) Safety Relief Valve.
• General: All safety relief valves shall be installed as per the approved P&ID.
• Safety relief valves are installed to automatically release the pressure if the pressure
exceeds the present limits.
• Each liquid line shall have relief valve connected to line (Threaded) without isolation
valve.
(C) Solenoid Valve.
• LPG Line
• Pneumatic Valve
It is a valve to open and close the gas automatically.
Installation of solenoid valve.
Solenoid valves are installed as per approved drawing.
The installation of solenoid valve on the beginning of the gas line to control the gas
from the tank into the building.
The solenoid is linked to the control panel, and will be threaded end.
(C) Ball Valve.
• Ball valves are used for isolate the system for power failure or any emergency
conditions.
Installation of solenoid valve.
Ball valves are installed as per approved drawing and its tagged in a proper sequence
the valve close & open condition.
Valve below 2” will be with Threaded fittings, and flanged end above 3’’
Page 23 of 62
6.7 Installation of Aboveground and Underground Pipe Network
(A) Installation of Aboveground and Underground Carbon Steel Pipes.
• The installation should comply with NFPA 58 Standards Installation of pipes to comply
with NFPA 54 & NFPA 58, WOQOD and local authority standards.
• Prefabricate pipe spools as per the approved layout drawing.
• Mount the necessary support in position and then install the pipes.
• Install the pipes as per the approved shop drawings.
• Secondary containment piping and fittings shall be used for pipes runs within
unventilated area, inside shaft and above ceiling as per Project Specification.
• The pipe sleeves shall be used in LPG internal piping inside the building unventilated
area, inside shaft and above ceiling as shown in approved drawing.
• Installation of carbon steel pipe sleeves.
a. Install the pipe sleeves as shown in the Approved drawing.
b. Insert Carbon steel gas pipe line inside the pipe sleeves as per the approved
drawing.
c. The Pipe shall be weld before the erecting the pipe in the position. Where
the pipe are bending Pipe sleeves elbow shall be made in two part by cutting
it and shall be joint again by welding process .(where ever applicable).
Spacer will be provided in between Carbon steel pipe and Pipe sleeve. After
fabrication of pipe and pipe sleeves shall be erect in the position as shown in
the approved drawing.
• Carry out the necessary fixing as per the approved standard procedures.
• Welding: pipes to be welded in accordance with qualified procedures using qualified
welders and calibrated welding machines. Procedures and welders shall be qualified in
accordance with ASME Boiler and Pressure Vessel Code: Section IX (refer to welding
procedure).
• Threaded pipe below 2” will be used for fittings (Valves, Regulator…) only.
• Flanges to be installed if diameter above 80 mm, then we can install unions or
connector.
• Connection of pipe branches from top or side of horizontal piping, reducers to be
installed where required.
• Gas pipes will be painted primer and two layers of yellow color to be identified from
other services.
Welding Procedure: Welding procedures for the LPG network shall be carried out according
to the following:
• Welding surfaces shall be thoroughly cleaned so as to be dry and from paint, oil rust,
and scale and other material, detrimental to weld quality.
• Each bead shall be clean of scale, oxides, dirt and other impurities before any
succeeding weld passes are made.
• Tack welding between the assembled pipes
Welding process
• First pass will be carried by SMAW (argon welds) using electrode Type E6013.
• The tack welds will be removed, followed by cleaning with a grinder.
• Continue welding of first pass at the tack weld location.
• Visual inspection of the first pass weld.
• Cleaning the first pass by grinder.
• Followed finally for the other pass by using SMAW, electrode Type E7018.
Page 24 of 62
• Each bead shall be cleaned of scale, oxide, dirt and other impurities and succeeding
weld process
Defects: Defects reverted by visual inspection of welds shall be repaired /rectified; the repaired
portion shall be re-examined
• Welding electrodes. The electrode shall be stored properly to prevent moisture
absorption and shall be handled in such a manner as to avoid damage to the coating
• All low hydrogen type electrodes shall be completely dry when used. These shall be
preheated in suitable oven at controlled temperature of 200-250C for not less than 4
hours and then used on the job.
• Electrode should be free when used from oil, grease, earth or any other matter.
• The pipes shall be cleaned thoroughly from any dirt (oils, dust etc.) followed by first
quote of oxide prime and then two layers of yellow paint for vapour lines and white for
liquid lines, as per the codes.
(C) Painting of LPG Piping and Spool.
The material surface to be painted shall be cleaned from any welding slag, dust, grease or
Debris Methods of surface preparation can be adopted e.g. degreasing, hand tool cleaning,
power tool cleaning. Painting shall be in 3 layer coating system.
Surface Preparation:
• Prior to cleaning the surface shall be checked for damages and all sharp edges and
weld spatter ground to give a smooth, gently radius profile.
• All oil, grease and any other contamination shall be removed by means of a water
soluble de-greasing. The degreased surface shall be tested for residual oil grease using
water droplets.
• Surface to be painted shall be cleaned by Sand papering.
• Surface preparation shall not take place when the relative humidity is greater than 85%
or when the surface temperature is less than 3 degree C above the ambient dew-point
PIPE INSTALLATION
Page 25 of 62
or when adverse weather conditions are anticipated or outside of day light hours on
exterior locations.
Cleaning Out
• Clean the entire sand papered surface prior to painting by brushing to remove spent
abrasive and dust residues or if permitted by using dry and oil free compressed air. The
compressed air used for cleaning must be free from oil and grease.
• Ensure that there is no spent abrasive lying in the vicinity of component that are being,
or have recently been, painted and that all painted surface are sheltered and protected
from any contamination by particular matter.
Application of Paint
• Paint shall be mechanically mixed prior to application; the mixture must be free of
lumps.
• Paint application on bare pipes & fittings shall be in accordance with manufacturer
recommendation and site conditions. (Airless spray or brush).
• Subsequent coat to be applied after proper drying of previous coat (manufacturer’s
recommendations to be followed) but within the recommended over coating period of
the paint at the metal surface temperature.
• Paint shall not be applied when;
- Rain, fog or mist is prevailing.
- Relative humidity exceeds 85% or the limit given by the paint
manufacturer. - Air or metal temperature is within 3 degrees C of the dew
point or air temperature is below paint manufacturers
recommendation.
• Each coat shall be allowed to cure for the time specified by the paint manufacturer.
• The final visual appearance of the paint film shall be such that it is free from runs and
sags, misses, orange peel, pinholes, fisheyes, over spray, dirt or garnet entrapment.
• All damages to the coating system shall be repaired as for original system. The repair
coating shall be applied by brush.
6.8 Installation of Underground HDPE Pipes.
The HDPE pipes will serve the LPG vapour for the underground network as per the approved
drawing. The pipes will be delivered in a roll or pipe length. The pipe roll will be installed in an
underground trench as follow.
Pipe will be as per approved submittal and have a yellow strips to identify the gas application.
A trench should be excavated according to pipe routing as per approved drawing from
finish floor level.
The bottom of the trench should be filled with soft sand up as per drawing.
The pipe will be laid over the soft sand layer.
A new layer of soft sand will cover the pipe
PAINTING OF PIPES
Page 26 of 62
A non-detectable warning tape will be laid over the pipe to mark the pipe location during
any future excavation.
A Tracer Wire will be laid over the warning Tape for pipe easy detection
Electro fusion welding will be made for joining of HDPE Pipe.
6.9 Pipe Leak Test/Pressure Test Description
• Upon substantial completion of the pipeline or major sections, the line will be cleaned
and hydrostatically tested to prove integrity of the pipeline section and to detect any
leakage prior to commissioning.
• Testing will be performed in accordance with the Project Specifications.
• Testing should be performed in the presence of the Engineer’s representative.
(A) General
• Always place the gauges at the end of the length under test.
• Take great care to avoid the joints and leaving sufficient space all-round the joints in
order to permit inspection and to undertake remedial measures if the joints be found to
leak during the hydraulic testing.
• Do not over pressurize the system under any circumstance.
• Provide all the equipment and materials for testing purposes. Remove and proper
disposal on completion of testing.
• Ensure that all test methods and procedures comply with his Health and Safety Plan.
(B) Prior ‐ testing
WARNING TAPE HDPE PIPE LAYING
Page 27 of 62
• Upon completion of the works, relevant sections shall do visual inspection to ensure the
correct installation procedure has been followed, and that the pipes and fittings are
adequately restrained and supported as per Project Specifications.
• Pipe joints, valves and fittings shall be checked carefully for loose bolts or connections
which might cause leakage and delay the execution of the tests.
• Keep all valves and control devices in open position.
• Ensure that materials and test equipment will be used for the whole procedure are
approved and the equipment is going to be used for the test has valid calibration
certificates.
(C) Test Procedure
• Safety will be a major factor during pressure testing to ensure a safe working
environment for all the site personnel and to safeguard plant and equipment prior to the
commencement of the test, toolbox talk will be given to all personnel identifying the
potential dangers of pressure testing and to make everyone aware that testing is ongoing
in the area
• Close and seal all nozzles / pipe ends with suitable plugs except the one used for the
nitrogen filling.
• Connect the nitrogen filled cylinder to the nozzle used for applying the pressure.
• Connect a calibrated pressure gauge.
• Start and monitor the pressure gauge until it reaches 50 psi.
• Close the valve and turn off the cylinder valve when the pressure is settled at 50 psi.
• Start the timer at this stage.
• Apply soapy foam on the pipe joints and at the pipe line to observe any leakage.
• Keep on monitoring the pressure gauge for any drop for 1 Hour.
• The piping maybe tested in sections or in total, depending on site requirements.
• If no leak or pressure drop is observed, then the pipe line has passed the test. If leak is
observed from the pipe line, stop the test for further investigation.
• Proceed with reinstallation only after satisfactory completion of the pressure testing.
• Raise the inspection request for witnessing the pressure testing to the consultant.
• Barricade the pressure testing area.
• Provide signboard on pressure testing is on-going in the area.
• All test equipment’s (cylinders, manifolds, pressure gauges etc.) will be inspected prior
to use to make sure they comply with the site safety requirements. All gauges shall
have a valid calibration certificate available for inspection.
• The requirements in this section apply to pressure testing of pressure piping systems.
• Pipework Test Pressure: The tightness test pressure shall be 6 bar. TEST DURATION
WILL BE 1 HRS. (As per NFPA 30 Chapter 5-Piping System, Section 5.6 Testing).
6.10 Electrical and Instruments Installation
(A) Detection System Installation:
(a) Gas Control Panel
• General Requirements: Control unit shall be minimum 32 channels; operating over a
temperature range of 0 to 50 degrees C
• Control unit shall be capable of monitoring of required detectors for the project
• Control unit shall be housed in a weatherproof cabinet suitable for wall mounting. The
control Panel shall have a reset button which restores the panel to its normal condition
when there is an interruption in power supply or emergency as there are chances of
Persons to leave the Kitchen without closing the Equipment valve.
• Gas control panel system shall be interfaced with main fire alarm control panel.
Page 28 of 62
• About the control panel: The control panel is from Sensitron and it can able to control
the required detectors. The control panel is installed as per approved drawing.
• The dimensions of the control panel are 486 * 288 * 148 millimeter ABS IP65 box.
• Install is measured at 180 centimeters from the surface of the floor and we put mark so
that the Distance 180 centimeter will be at the top edge of the control panel.
• The control panel on the wall and keep above spirit level to adjust the control panel.
• Adjust the control panel and put signs inside the four ad hoc holes to install the control
panel.
• Mark on the wall and make four holes with a diameter of 6 ml Drill and put inside Roll
plug the plastic. Then install the control panel on the wall using the appropriate screws
Note: Installing the control panel inside the wall. In this case the control panel is
installing in with cement. Without nails and roll plug.
• Install the control panel and connect the cables and making connections.
(b) Gas Detectors:
• Explosion Proof Gas Detectors shall be installed in the tank area as per approved
drawing. The Gas Detectors shall be dust proof installed for inside the building as per
approved drawing.
• Gas detector is a device to detect any gas leak in the area surrounding it. Gas detectors
are installed as per approved drawing, there are two types of it, first dust proof and
second are explosion-proof.
• Measure 30 centimeters from the floor. So that the Distance 30 centimeter will be at the
Lower edge of the gas detector.
• Gas detector on the wall and keep above spirit level to adjust the detector.
• Adjust the gas detector in the wall. We put signs inside the two holes is using for
installation of the gas detector.
• Signs on the wall we have to do two holes with a diameter of 6 ml Drill and put inside
Roll plug the plastic. Install the gas detector on the wall using the appropriate screws.
• Put the cable inside the detector and doing the connection after installing the detector.
• Install Gas detector for double containment pipe by installing a Tee-joint connection
with in Containment pipe as per approved drawing and interconnected with centralized
gas detection system (where ever applicable).
Page 29 of 62
(c) Sounder
• Sounder used shall be 32 Tone Red color sounder and minimum audibility shall be 115
dB at 1 meter.
• Gas control panel shall be installed and connected to the gas leak detectors.
• The detectors shall be installed in their place as per the shop drawings, WOQOD &
NFPA regulations.
• Emergency push buttons, solenoid valves and detectors needed shall be installed in the
tank room and equipment location.
• Conduit pipe with the cables inside shall be installed running parallel with the LPG line.
Page 30 of 62
• It is a device to alert to the presence of leaks in
the gas system, there are two types of it’s (with
flashlight and without flash).Sounder is to be
installed as per approved drawing
• Measure 180 centimeters from the floor.
• Put the sounder on the wall so that it is the
middle of the sounder at a distance of 180
centimeter. Previously identified.
• Put signs on the wall in places Installation Holes
and make holes diameter of 6 ml in places Installation Holes in with Drill 4 Putting Roll
plug in the hole did it before. Then install the sounder on the wall using the appropriate
screw.
(d) Emergency Push Button:
Emergency push button is used to open and close the gas manually and usually we install near
to the:
• Installation is measured at 150 centimeters from the surface of the floor and put mark
so that the distance 150 centimeter will be at the Lower edge of the emergency push
button.
• Put the emergency push button on the wall and keep above spirit level to adjust the
emergency push button.
• After adjusting the emergency push button put signs inside the two ad hoc holes to
install the emergency push button.
• After marking on the wall make two holes with a diameter of 6 ml Drill and put inside
Roll plug the plastic. Install the emergency push button on the wall using the
appropriate screws.
• After installing the emergency push button put cables and making connections for it.
(e) Junction Box
• It is a plastic box used to assemble the
cable coming from the emergency push
button and solenoid and sounder. And
install control board inside it to control
solenoid valve and sounder and other
devices.
• Install the junction box on the wall
surface with four screws or install it
inside the wall using cement and in path
way have to use spirit level to adjust
(f) Electrical Cables:
• Electrical cables are responsible for linking the gas detection equipment’s like control
panel, detectors, solenoid valves & push button so that it is extended inside the PVC
pipes from each other to Point to point.
Page 31 of 62
Installation of Electric Cables:
Pull the cables inside the G.I. pipe from the point to another point by using the wire
spring. The cables are used type of fire resistant to the work of all connection
(g) G.I Conduit:
It is used to extend the cables from device to other such as gas detector and solenoid
valve and sounder and emergency push button etc.
Installation of G.I. Conduit
Conduit are connected together by coupler and placed under the floor at a depth of 10
cm or more and are fastened to the floor in with cement or nails and Wire strap.
6.11 Quality Control and Records
(A) Inspection and Testing
• The Inspection and Test Plan (ITP) for Installation Full system summarizes the various
characteristics to be checked.
• The concerned Project Engineer will be responsible to ensure stage wise compliance
for these operations and the QA/QC Engineer will carry out quality control checks and
report the inspection results.
• Work activities ITP is developed and provided in Attachment – 1
(B) Documentation
Inspection Request (IR) Form will be submitted for the installation of sleeves with
adequate notice.
Consultant Inspection Request (IR) Form shall be followed for all site work activities and
will be the verification documents for meeting the requirements of the project.
The QA/QC Inspector will be responsible for completing Inspection Requests for these
activities and record all checked items in related Checklists for Installation of pipes
(Refer to Attachment – 2)
- Forms and attachments
Document Number Title
Attachment 1 Inspection and Test Plan – Installation of LPG
system
Attachment 2 Inspection Request Format
Attachment 3 Risk Assessment – Installation of LPG system
Attachment 4 Environmental Risk Register– Installation of LPG
system
Page 32 of 62
Annexure 1
Inspection & Test Plan (ITP)
For
Installation of LPG System
Page 33 of 62
Doha Port Redevelopment Project ‐ Combined Mina District & Seawater Diving Pool
Installation of LPG System
INSPECTION & TEST PLAN (Rev. 0)
S. No. Activity
Description
Inspection
/ Test
Method
Document
References
Acceptance
Criteria Frequency Responsible
Person (s)
Action
REMARKS
MC CSC PMCM TPA
Prior to start work
1
All
necessary
permits
obtained &
approved
Submit
application
to the
concerned
authority
Project
Specification,
IFC Drawings
Approved
Permits
Prior to
start of
works
Sr.
Construction
Manager,
QA/QC
Engineer
H R R N/A Work
Permits
2
Method
Statement
submitted
and
approved
Approved
submittals
Project
Specification,
IFC Drawings
Approved
submittals
Prior to
start of
works
Sr.
Construction
Manager,
QA/QC
Engineer
H H R N/A Approved
submittal
3
Task Launch
meeting
shall be
conducted
HSE
Records
Project
Specification,
IFC Drawings
HSE
Records
Prior to
start of
works
Safety
Officer,
Site
Engineer
H R R N/A
TBT
attendance
Sheet
Page 34 of 62
prior to
start work,
shall be
recorded
4 Survey &
Setting out
Submitted
and
reviewed
survey
reports
IFC Drawings As per IFC
Drawings
Per
activity
Surveyor,
Site
Engineer,
QA/QC
Engineer
H R R N/A Survey
Report
Installation Works
5
Inspection
of all
Copper
Pipes,
Fittings and
Accessories
Visual
Inspection
Project
Specification
Approved
submittals
Prior to
start of
works
Sr.
Construction
Manager,
QA/QC
Engineer
H W S N/A MIR
6
Laying of
Pipes,
Alignment
and Levels,
Pipe
Support and
Brackets
Visual /
Physical
Inspection
Project
Specification,
Shop
Drawings
Inspection
Request
Each
location
Sr.
Construction
Manager,
QA/QC
Engineer
H W S N/A WIR
Page 35 of 62
7
Partial
network
Pressure
test
Visual /
Physical
Inspection
Project
Specification,
Shop
Drawings
Inspection
Request
Each
location
Sr.
Construction
Manager,
QA/QC
Engineer
H W S N/A WIR
8
Final
Inspection
Refrigerant
Copper
Pipes
Installation
and Testing
Visual /
Physical
Inspection
Project
Specification,
Shop
Drawings
Inspection
Request Each area
Site
Engineer,
QA / QC
Engineer
H W R N/A WIR
Legend
W ‐ Witness (attendance, expected, Signature on Check sheet) WIR ‐ Work Inspection Request PMCM ‐ Project Management
H ‐ Hold Point IFC ‐ Issued for Construction CSC ‐ Construction Supervision Consultant
S ‐ Surveillance (random Surveillance, no signature required) I ‐ Perform the activity MC ‐ Main Contractor
R ‐ Review Record TPA ‐ Third Party Inspection Agency
Page 36 of 62
Annexure 2
Inspection Request Form
Page 37 of 62
Page 38 of 62
Annexure 3
Health and Safety Hazard Identification
and Impact /Risk Assessment
For
Installation of LPG System
Page 39 of 62
RISK MATRIX
RISK ASSESSEMENT: Installation of LPG system
SAFE ZONE = 1 ‐ 4 MODERATE ZONE = 5 – 9 DANGER ZONE = 10 ‐ 12 EXTREMELY DANGER ZONE = 15 ‐ 25
SEVERITY
PROBABILITY Negligible Marginal Serious Critical Catastrophic
Highly Probable 5 10 15 20 25
Probable 4 8 12 16 20
Occasional 3 6 9 12 15
Remote 2 4 6 8 10
Improbable 1 2 3 4 5
Page 40 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
1
Transportation,
Mobilization &
Storage of materials:
Site Deliveries
Slip, trip, fall,
Fall from height
Falling objects
Unsafe Act / Unsafe condition
Struck by vehicle
Personal Injury,
fatality
Property damage
Loss of company
reputation
4 4 16
1‐ All drivers / operators must be in possession of valid
Qatari driving license
2‐ All vehicles / plant must be compliant with Qatar
traffic & road regulations related to registration, follow
project traffic management plan.
3‐ All vehicles must kept within their SWL and always
follow manufactures recommendations when treating
load
4‐ All drivers entering site must be HSE inducted and
must undergo driver awareness training
5‐ Suitable routes, roadways and parking (firm, even
surfaces, routes to be marked with directional
signage’s), speed, limits, one way routes, lights etc.
6‐ Suitable segregation of pedestrian and vehicles e.g.
pedestrian
7‐ All reversing vehicles to be controlled by a trained
banks man
8‐ All mobile plant & equipment to have audible
reversing alarm
9‐ No use of mobile phones whilst driving8‐ Blind spots
to be mitigated by appropriate mirrors.
10‐ All vehicles must be fitted with flashing beacon light
prior to entering site
11‐ All drivers entering site must be HSE inducted and
must undergo driver awareness training
12‐ All subcontractors, suppliers, visitor drivers must be
provided with visitor induction prior to entering site. - Goal post to be made to restrict the vehicle entry
and access controller/security/flagman to be assigned
to control vehicles.
14‐Vehicles restricted to move near the racks. only
allowed specific unloading area
15‐ All over sized loads and large vehicles to be
escorted from site entrance by another site vehicle and
4 1 4
CM
Site
Engineer
Supervisor
Foreman
Page 41 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
/or banks man where possible, ensure loads well
secured and lashed.
16‐ Access to trailer only, operatives not to climb on
loads, access via ladder if no fixed access is available on
the trailer
17‐ Only authorized personnel within the working area,
hard barriers used with restricted access within the
unloading area.
18‐traffic system will be implemented to reduce the risk
of the vehicle colliding with storage rack by making
barrier, designated Safe route, flagman and specific
unloading area
19‐ Lifting plans to be provided for all lifts using crane,
Large or over size loads to be assessed within the lifting
plan for accessing the lifting points. Scaffold and/or
ladders access or MEWP to be used where possible.
20‐ Ensure area used for lifting/unloading operation is
barricaded and necessary caution and warning signs
and flag mans are placed, positioned before
commencement of work task, operation.
21‐ Loads palletized and pre slung where possible,
utilize lifting plans for all lifts
22‐ Ensure mandatory PPE is made complaint for all
employees.
23‐ Laydown area planned to avoid reversing, drawings
within logistics plan.
24‐ A competent banks man deploy with moving
equipment.
25‐ Use seat belt, no overtaking and no tailgating while
driving.
26‐ Ensure on arrival inspection of a heavy vehicle is
carried out by DOMOPAN area HS Officer.
Page 42 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
2
Material Inspection &
Storage
Over stacking of materials
Improper manual handling
Poor illumination.
No ventilation.
Over load
Mixed materials.
Fall of materials
fire
Minor injury/Major
injury, Fatality,
Property / Asset
damage
Loss of company
reputation
4 3 12 - Pre‐job briefing prior to any task to be done
considering updated approved RAMS. - Maintain a height of stacked materials less than 1
meter. - To be Provide sufficient illumination as per QCS 2014
Section 11, Part 1.5.3. - Provide suitable ventilation for workers and to
maintain the good condition and quality of the
materials. - Provide suitable fire extinguishers.
- Ensure Chemicals/flammable materials shall be
segregate and stacked in separate designated location. - Ensure to provide mandatory PPE like hand gloves
(cotton gloves),safety goggles, etc.
4 1 4
CM
Site
Engineer
Supervisor
Foreman
Page 43 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
3
Preparation to start
the work.
Lack of Supervision
Incompetent workers
Lack of information regarding
the activity
Improper communication
Personnel injury,
property damage,
Loss of company
reputation
4 3 12
1‐ The Initial Site Safety Induction, Pre‐Job briefing ,
Toolbox Talk, Safety Awareness Meetings will be
conducted, if applicable, required permits must be
obtained prior to commence the work
2‐ Ensure all the necessary control measures has been
communicated to all levels.
3‐ Proper work plan and Ensure adequate control
supervision must be in place.
4‐ Appropriate use of mandatory PPE such as Hard hat,
coverall, Safety goggles, Safety gloves, hi‐viz vest, safety
shoes etc.
5‐ Ensure the evacuation, incident reporting procedure
has been briefed to all level and in case of Emergency,
DOMOPAN evacuation procedure must be followed.
6‐ Ensure all the plant and equipment entering in the
site must be inspected, have a valid 3rd party certificate
and vehicle registration.
7‐ Adequate safe work environment (i.e. lighting,
welfare facilities, emergency response, etc.) must be
provided.
8‐Pedestrian access to be provided and marked.
9‐Logistic plan to be implemented and access roads
properly marked.
10‐traffic control system including speed limiting will be
implemented to reduce the risk of the vehicle colliding
with other vehicle, designated Safe route, flagman and
specific unloading area. - Speed control including hump and warning signs.
12‐barrier/tire stopper to prevent hitting damages for
building
13‐ Ensure all vehicle entering construction site must
have a gate pass.
14‐ Ensure that necessary Work Permits, including
interface permits where applicable will be obtained
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 44 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
with all required safety precautions, prior to start any
activity.
15‐ Ensure Housekeeping and Waste Management
(where applicable) has been done.
16‐ Provision of emergency contact details, procedure,
First aiders, First Aid Kit / station / Clinic with qualified
personnel will be available at the site.
17‐ Provision of welfare facilities; rest areas, toilets,
hand washing facilities, mess hall, fresh drinking
water…
18‐ Close supervision is always mandatory.
19‐ Hard copy of approved MSRA shall be made available
at the work site.
Page 45 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
4
Lifting operations:
Installation of LPG
tank, pipes, use of
boom Truck / mobile
crane
Equipment failure, Overturned,
Collision with Other Vehicles,
Falling of load,
Uncontrolled / Unstable Load,
Struck against objects,
incompetent operatives,
Fatality, personal
injury, property /
asset damage,
5 4 20 - Permit system to be implemented for all mechanical
lifting work. - Lifting plan should be in place for critical lifting.
3‐ Pre‐job briefing talk, Toolbox Talk and Pre lift
meeting to be performed before the start of work
activities.
4‐ Safe lifting procedure must be followed.
5‐All lifting tools and crane and operators’ must be
certified by third parties.
6‐ Periodic inspection of lifting equipment / accessories
to be carried out and valid 3rd party certificates must
be provided, maintained.
7‐ All lifting equipment, gears shall be assessed
correctly as per work task with safe working load and
other safety factors. Avoid plant & equipment use
inside storage area, operating with gasoline fuel.
Battery operated plant will be priority.
8‐ Damaged lifting equipment shall be removed from
site.
9‐ Only 3rd party trained personnel shall be allowed for
rigging, lifting activities.
10‐Unloading work activities and identified, appointed
person to ensure safe subject operations, work task.
11‐Before lifting all loads are checked to ensure they
are within the safe working load of the equipment.
12‐Barricaded the lifting radius, isolated from
workforce display signage.
13‐ Signaling to lifting/unloading operation shall be
assigned to one competent person only.
14‐ Operator shall never leave his position at control
when load is suspended.
15‐ Always try to keep load clear of the personnel
working below.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 46 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
16‐ Personal protective equipment shall be strictly
enforced during the operation.
17‐ Tag lines, secured load provision shall be in use to
guide the load in safe manner.
18‐Movement of vehicle controlled by a banks man, All
needed/ necessary PPE’s will be worn by employees
involve in work activities.
19‐ Always ensure that all lifting/unloading mechanical
plant, equipment, aids and supporting outriggers,
stands must be on a firm and level ground.
20‐ Ensure area used for lifting/unloading operation is
barricaded and necessary caution and warning signs
and flag mans are placed, positioned before
commencement of work task, operation.
21‐ Close and effective supervision shall be ensured
during lifting/unloading operation.
22‐ Provision of emergency contact details, procedure,
First Aid Kit Clinic with qualified personnel will be
available at the site.
23‐Safe load and the load radius indicators will be
checked periodically for accuracy.
24‐Should ensure awareness of the risks involved, but
will not eliminate human error.
26‐ Assess the area thoroughly for blind spots, proper
communication between operator & rigger.
27‐Lifting operation shall be carried out in presence of
certified and approved lifting appointed person.
28‐ Lifting operation shall be thoroughly supervised by
a certified and approved lifting Supervisor.
Page 47 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
5
Working inside
Excavation
Cave in
Soil collapse
Obstructed access
Scattered rocks
Unprotected edge
Proximity to moving equipment
Materials near the edge
Contact with existing services
Presence of toxic fumes or
gases
Minor/ major injury
Fatality
Company loss of
reputation
5 4 20 - Ensure pre‐job briefing prior to start the task.
approved RAMS to be available & ensure valid PTW
obtained.
2.Ensure proper coordination of MEP team to Civil team
prior to entering excavation to obtain clearance
access and egress should be free from any obstruction
3.Ensure hard barriers are used for edge protection
Provision of safety signage’s and warning lights
Use of CAT and Genny to isolate/mark the buried
service
4.Ensure good housekeeping of the area
5.Maintain proximity to moving equipment
6.Remove any materials/debris near the edge
7.Ensure good condition of shoring materials or netting
8.Ensure appropriate PPE’s are worn prior to entering
excavation area
9.Daily Inspection of Excavation by Competent Person - Ensure underground utility drawing is verified prior
to the commencement of excavation and is made
available at the work site. - Ensure excavation work permit and work inspection
report are obtained and are made available on site. - Daily inspection of excavation by a competent
person using excavation checklist. - Ensure adequate safe access/egress platform should
be provide as applicable. - Refer to QCS 2014 section 11 part 1.5.4 for additional
control measures.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 48 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
6
Working at height /
using podium ladder
or mobile scaffolding.
Materials and debris scattered
on edges
Incomplete scaffolding
No inspection of the scaffolding
Incompetent workers
No supervision
Falling of materials
slip, trip and fall
Falling of person
Collapse of the Working
Platforms.
Personal Injury,
fatality
Property damage
Loss of company
reputation
5 4 20
1‐ Avoid and minimize works at height, assemble at
ground level wherever practicable.
2‐ All employees must be provided be in‐house training
on safe working at height and must be given strict
instructions never to climb racking
3‐ Supervisor to conduct safety briefing (PRE‐JOB
BRIEFING ) prior to work commencement
4‐Disciplinary action to given to for Unsafe act whilst
working at height
5‐ Competent Supervision to be provided at all times.
6‐ Competent scaffolding inspector should inspect all
the scaffolding before use and recorded. - Only use green tagged scaffolding.
- All scaffolding component inspected or retighten in
every three months.
9‐All works must follow the correct sequence. 100% tie
off and use of safety harness with double lanyard
should be used where a fall from height is likely
10‐ Adequate structural support (i.e. bracing, cantilever
secured planks, support tie‐ups, toe boards, safety net,
etc.) to be provided as required
11‐ No works to be carried out below operatives
working at height, exclusion zones with warning tape /
hard barriers to be provided below with signage clearly
placed
12‐ Where applicable watchman to be provided below
works at height
13‐ Ensure operatives are provided with work at height
training by an approved third party agency.
14‐ Ensure scaffold inspection is carried out by a
certified scaffold inspector at regular intervals not
exceeding seven days since the last inspection.
4 1 4
CM
Site
Engineer
Supervisor
Foreman
Page 49 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
15‐ Ensure users are performing visual inspection of
scaffold prior to use by – Don’t use it if any missing
components identified.
16‐ Maintain three points of contact while
ascending/descending a ladder.
17‐ Safe handling, use and storage of all loose
materials, sharp objects and small components, packs
of fixing and tools and equipment must not be stored
near leading edge at height. Tools and equipment to be
attached to person, access point to prevent falling and
must be stored inside tool box whilst working at height.
18‐ Flooring kept dry and quality maintained. All
employees to be trained to clean and dry and spillages
immediately.
16‐ Ensure racking, platform is designed to be suitable
for loads and co‐workers on job.
19‐Adequate signs to be clearly fixed to racking stating
the maximum loads (SWL) configuration
20‐ Any defects / damages to racking to be reported
immediately
21‐ Regular Tool box talks to be conducted for
operatives working at height
22‐ All temporary working platforms (scaffold systems)
shall be erected by trained and competent personnel
only.
Page 50 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
7 Hot Work:
Welding, cutting,
Grinding
Slip, trip, fall,
Metal Splatters, Flying, foreign
particles, Explosion, Radiant
energies, Release of gases,
Naked flame, Hot surfaces, fire,
Electrocution
Burns, Injuries to
body, Property /
asset damage,
Company loss of
reputation
5 4 20
1‐Pre‐job briefing talk, Toolbox talks to be provided,
performed before the start of work activities. Permit to
work system must be followed.
2‐The person involved with hot work activities shall be
trained and competent.
3‐The hot work area shall be safe & suitably arrange,
barricade and appropriate signage provision to restrict
unauthorized entry.
4‐The appropriate and suitable PPEs (Safety shoes,
gloves, eye protection, face shield, apron, coverall)
must be in use as applicable.
5‐Provide adequate ventilation and fire prevention,
protection in the vicinity (i.e. fire extinguisher, fire
blanket, sand, water, & fire watchman, etc.).
6‐Daily inspection of hot work associated power tools
and equipment prior to start the work.
7‐Hot work permit must be available and approved and
associated safety precautions must at place and
maintained.
8‐First aid, emergency rescue provision, contact details
shall be available in case of injuries/emergency.
9‐ Certified fire watcher will remain at site of the hot
work for 30 minutes after the hot work is completed to
ensure that the work area is safe, secured and free
from the risk of fire.
10‐The hot work permit shall be closed 1 hour before
the end of the shift.
11‐Proper & adequate grounding/earthing should be
available for electric generated equipment.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 51 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
8
Installation of Pipes,
Fittings, Valves,
Regulators, detection
system, Cable tray
and Control Panel
Installation
Defective tools & equipment,
Failure of tools, equipment,
gears.
Falling of the load,
Slip, trip, fall
Suspended load,
Sharp edges
Pinch point
Incompetent personnel,
Overhead structure
Personal injury,
Property damage,
company
reputation,
4 4 16
1‐Pre‐job briefing talk, Toolbox talks to be provided,
performed before the start of work activities. Permit to
work system must be followed as applicable.
2‐Ensure the material should be stocked properly.
3‐All lifting gears, tools should be third party certified
and color coded.
4‐Keep the working area neat and tidy to avoid tripping
& fall hazards.
5‐Adequate exclusion zone with warning signs should
be provide around working area.
6‐No un authorized personnel allowed in the working
area. - Pre check the tools, equipment, gears prior to start
the activities.
8‐ Wear appropriate PPEs i.e Safety shoes, Helmet,
Goggles, Coverall, gloves as applicable.
9‐ Keep always access way clear from the obstructions.
10‐Hold the load by providing the tag lines if applicable.
11‐Deploy competent operatives for carry out the task.
12‐Keep always body parts away from the Line of fire.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
9
Painting work
Defective tools, slip trip fall,
hazardous substances, in
competent operatives, vapors,
Improper handling of
chemicals, spill, Fire
Personal injury,
health issues in case
of inhalation,
soil/ground
contamination,
4
4
16 - Pre‐job briefing talk, Toolbox talks to be provided,
performed before the start of work activities. - A comprehensive COSHH assessment should be
carried out & briefed about the SDS to all involve crew
members. - Ensure competent operatives for performing the
task. - Proper handling/storage of painting material at site.
- Pre check the tools prior to start the activity.
- Adequate PPEs i.e coverall, Safety glasses, Safety
shoes, mask, helmet. - SDS & COSHH assessment should be in place.
- First Aid & emergency arrangements should be in
place.
4
1
4
Page 52 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R - Appropriate fire extinguisher should be in nearby
area of the work. - Spill emergency response arrangements should be
in place.
10
Handling of
COSHH materials
Leaks,
Improper waste handling
Improper storage
Neglect of MSDS, Chemical
comes in contact with body
parts, inadequate ventilation in
storage area and ingestion,
Skin problem
Breathing problems
Environmental
problems
Fines
Company loss of
reputation
Ill health
4 4 16
1‐Ensure MSDS & COSHH Assessment to be briefed
& explained regularly, to users.
2‐Waste Management Plan to be followed.
3‐Waste segregation and collection point to be
made available. Containment and covering of solid
waste.
4‐Awareness and training material to be provided to
operators relating to waste management, and good
practice.
5‐Use of licensed waste contractor for waste
collection and disposal, with scheduled waste
collection.
6‐The COSHH container to be used for storage of
chemical
7‐Training to be given.
8‐ Wear chemical‐resistant hand gloves, safety
glasses, suitable mask, safety footwear, in
conjunction with other mandatory PPEs.
9‐ Ensure provision of First Aid treatment as per SDS.
10‐ Ensure adequate ventilation in the storage area.
11‐ Prevent unauthorized entry into the storage area.
12‐ Wash hands thoroughly before eating and
smoking.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 53 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
13‐ No smoking at the work site – Smoking is allowed in
the designated smoking area.
11
Hand & Power Tools
use:
Slip, trip, fall, Flying,
foreign particles, Fire
Electrical shock, Electrocution,
Struck by tools.
Cut, Injuries to
body, burns.
Fatality.
Company loss of
reputation
4 4 16
1‐ Pre‐job briefing, Toolbox Talk shall be provided with
subject work task, including hand and power tool safety
procedures.
2‐ Hand and power tools shall be used, inspected, and
maintained in accordance with the manufacturer’s
instructions and recommendations and shall be used
only for the purpose for which designed.
3‐ Hand and power tools shall be in safe operating
condition before use. All power tools shall be
periodically inspected and color coded by site PMV
DOMOPAN Electrical Duty Holder to assure their safe
operating condition and proper maintenance.
4‐ Only certified / trained workers shall be allowed to
operate the tools / equipment. Keep always body parts
away from line of fire. Hold the hand/power tools firmly
and keep body posture in safe position.
5‐ Secure long sleeved and loose shirts when working
with rotating tools.
6‐ Secure tools when working on height by keeping them
in tool belt.
7‐ Defective tools shall not be used. All damaged or worn
tools to be returned to the store.
8‐ Do not transfer, move, and pull the machine with the
help of its electrical cord. 9‐ Ensure the work
area to be dry to avoid slips and electric shock.
10‐ All safety guards, handles etc. shall be in position,
and not to be removed from the machine.
11‐ Make provision for tool bag with belt while working
at height.
12‐ Inspect tools for loose and defective parts. Report
and replace immediately. 13‐ Appropriate
ventilation system and personal protective equipment
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 54 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
shall be used when performing work with Hand / Power
tools.
14‐ Provision of emergency contact details, procedure,
First Aid Kit Clinic with qualified personnel will be
available at the site.
12
Manual Handling
Slip, trip fall,
Poor body posture
Incompetent operatives
Improper handling techniques
Excessive load
Sharp edges
Pinch point
Muscular problem,
backache, hand &
finger injury,
property damage 4 4 16
1‐ Pre‐job briefing talk, Toolbox Talk to be conducted
regarding Heat Stress before the start of each activity.
2‐ Competent operatives for perform the task.
3‐Use mechanical aid for load handling as much as
possible.
4‐Assess the load properly prior to lift.
5‐Use comprehensive manual handling techniques for
carrying the load.
6‐Carry the load as per specified load limit for an
individual.
7‐If load to heavy seek assistance of other person.
8‐Keep always body posture in safe position to avoid
muscular problems.
9‐Use appropriate PPEs i.e Safety boots, coverall, Hand
gloves, Safety goggles.
10‐Hold the load firmly during carrying and keep near
to upper part of the body as much as possible.
11‐Always follow the safe work practices.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
13 Pressure Testing Uncontrolled
release of the
pressure
Improper fitting of pipes
Lack of or
unsafe Pipe
supports
High pressure
Burst pressure
Personal Injury
Damage to
property/
equipment
Company loss of
reputation
5 4 20
1‐Pre‐job briefing, Toolbox talks, safety induction, to be
conducted and specific training provision, before the
start of each activity. Appropriate permit to work
system should be followed.
2‐Only authorized, trained, competent person should
carry out subject testing.
3‐The work location shall be barricade and appropriate
signage must be display to restrict the unauthorized
entry
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 55 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
4‐The safe work environment (i.e. safe walk way,
adequate ventilation, housekeeping, suitable lighting,
etc.) shall be provided and maintained.
5‐Fire prevention and protection provision. No open
flame, ignition source nearby this testing area.
6‐The materials (i.e. pipe line, their joints, their elbow,
etc.) for testing shall be secured adequately against
uneven movements. Adequate supports to be provided
according to the load calculations for the both sides of
the pipes.
7‐All hazardous materials must be used, store, dispose
in proper manner.
8‐Operatives, examiners shall always use suitable PPE
for the assigned job. Inspect the test location prior to
testing operations. Responsible personnel shall be
provided at all times during the test period.
9‐All pressure, other testing equipment shall be fully
operational and regularly maintained and calibrated.
10‐ The pressure shall be raised gradually with safety &
time factor and monitor for any leakage, or any uneven
outcomes. The required pressure gauge installation
shall be safe enough to monitor the development of
pressure.
11‐Caution tags shall be used to identify equipment and
lines under test with all safety precautions.
12‐Full face shields/safety goggles, gloves, shoes shall
be worn when checking for leaks during pressure
testing.
13‐All personnel shall be maintained a safe distance
away from the lines during pressurizing.
14‐In the event of a failure during the pressure or other
test, the system shall be immediately depressurized or
safety measures must be obtained, provided.
Page 56 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
15‐ PTW shall be obtained from DOMOPAN PTW
coordinator prior to the commencement of pressure
testing.
14
Night Works
Poor illumination ‐Dark Area
Poor Visibility
Eye fatigue
Personal Injuries for
unseen hazards
Headaches
Company loss of
reputation
4 3 12
1‐Illumination lux shall be provided confirms to QCS
2014 Indicated in section 11 and Appendix 2.
2‐ Delivering Pr‐job briefing dealing with night shift
safety.
3‐ Illumination level shall be monitored prior to start
the job by respective Site Engineer.
4‐Construction areas, aisles, stairs, ramps, offices,
storage areas and work place must have illumination.
5‐Replace defective lights and clean lights regularly.
6‐ Ensure the safe access and egress for the work
area.
7‐Ensure the welfare facilities such as Water and
Toilet etc,
8‐Emergency rescue team availability within job site.
9‐Night work procedure shall be followed
10‐Ensure close supervision.
11‐Suitable PPE for all workers
12‐ Obtain night work permit
13‐ Use hi‐viz vest in conjunction with other PPE
while working at night.
14‐ Ensure workers are having a good sleep before
they come to work.
15‐ Follow work rest break schedule.
16‐ Sleeping at the work site and under or behind the
vehicle and equipment is strictly prohibited.
17‐ Ensure workers are fit for night works.
4 1 4
CM
Site
Engineer
Supervisor
Foreman
15
Exposure to Adverse
Heat Stroke, Heat Exhaustion,
Heat Cramps,
Absenteeism
Suspension of task
Recovery / medical
expenses.
4 4 16
1‐ Pre‐job briefing Talk, Toolbox Talk to be conducted
regarding Heat Stress before the start of each activity.
2‐Provision of shelter for rest, provision of adequate
drinking water, Employee orientation on summer /heat
stress safety.
4 1 4
CM,
Site
Engineer
Supervisor
Page 57 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
or Hot Weather
conditions :
Heat Rash,
Dizziness,
Loss of company
reputation.
3‐ Make sure that all workers have easy access to cold
drinking water and other welfare facilities.
4‐Provision of ventilation like fans/ventilators or airconditioned
rest areas.
5‐Make sure that weather monitoring and flag system
are implemented
6‐ In case of excessive heat, work in shifts is required or
rotation of work is to be maintained with required
facilities.
7‐ Regular scheduled rest periods must be given to
workers.
8‐ Ensure work is scheduled as per revised site work
timings.
9‐ Consider work stoppage when temperature reaches
to critical level as required by local regulation.
10‐ Provision of emergency contact details, procedure,
First Aid Kit Clinic with qualified personnel will be
available at the site.
11‐work breaks as per weather monitoring (more rest
break will allowed during high temperature).
12‐ Follow Project Heat Stress Management plan.
Foreman
16
Housekeeping and
Waste Management
Accumulation of combustible
materials with fire risk,
slip, trip, fall,
Hand injury, head
injury, eye injury
etc,,
4 4 16
1‐ Pre‐job briefing, Toolbox Talk shall be provided and
Good Housekeeping to be maintained.
2‐ Access/egress path must be maintain, no obstruction,
unwanted materials in between approach path.
3‐ All Hazardous, combustible waste, fire load materials
must be disposed of daily in proper manner within an
area designated by the Principal Contractor.
4‐ Observe, maintain safe and proper storage of
materials, including daily generated waste.
5‐ Highlight, protect, and prevent potential hazards from
any protruding sharp edge materials with warning tape
or cones, caps.
4 1 4
CM,
Site
Engineer
Supervisor
Foreman
Page 58 of 62
RISK ASSESSEMENT: Installation of LPG system
No Task & Activity Hazard/Risk Consequences Initial Risk Control Measures Residual
Risk
Responsibility
S L R S L R
6‐ Protect, prevent all electrical cables from potential
hazards with proper routing with safety precautions.
7‐ Proper use, care, maintenance of PPE as per work
task.
8‐ All the loose, flying, falling objects, materials with
must be organized, secured properly.
9‐ Sufficient waste receptacles be provided in food
service area and used for the disposal of waste food.
10‐ Provision of emergency contact details, procedure,
First Aid Kit Clinic with qualified personnel will be
available at the site.
10‐ Good standard of housekeeping shall be maintained
before, during and after the completion of the work.
11‐ No smoking at the work site‐Smoking is allowed in
the designated smoking area only.
17
Emergency
Lack of Awareness
Slip / trip / fall
Injuries, fatalities
Company loss of
reputation.
4 4 16
1‐Reminding Emergency procedures during each
STARRT briefing.
2‐Follow evacuation plan
3‐Accesses / Egresses to be free of any obstructions
4‐Exit & Ways to master points to be guided by clear
displayed signs.
5‐Assign first aiders like area respective engineer /
supervisor / group leaders: mention their names /
contact numbers/ locations: all these to be displayed
anywhere on site.
5‐Provide first aid kits / boxes all over work tasks
locations
6‐Medical screening of all existing on site is mandatory
periodically.
7‐The provision of Site first aid station / clinic leaded by
a doctor / nurse is mandatory.
8‐Provide workers with Periodic fire / emergency /
evacuation drills
9‐Provide clear designated Assembly points.



