Fire Rating Certificate for the Doors

Hollow Metal Door sub-contractor payment terms issue

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject        : Regarding Hollow Metal Door sub-contractor payment terms issue.

Dear All,

With reference to above mentioned subject, we are attaching a mail from xxx on14thxxx.kindly review/decide their payment terms which is self-explanatory that they are payment terms not matching with nomination document issued by your office.

Furthermore any advance which is being paid more than 10% the main contractor is liable to pay only 10% additional amount above the 10% as advance must be paid by the employer and should not be deducted from the main contractor.

So, kindly review and request to do needful.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top