Free Issue Material‐ Bathtub quality issues
Our Ref: xxx
Date: xxx
To : xxx Contracting Middle East,
P.O.Box xxx,
Dubai, UAE
Attention : Ms. xxx
: Project Director
Project : xxx Tower Views, Dubai
Subject : Free Issue Material‐ Bathtub quality issues
Dear Mr. xxx,
We again remind you that as per the Sub-contract Agreement, Appendix 2, scope of work, item 2, the bathtubs are a free issue item, selected, inspected, procured and then delivered to our factory by the Main Contractor.
We have requested in our letter ref: xxx dated 18thFebruary xxxx to verify that the delivered bathtubs meet the quality requirement in order not to disrupt the production and delivery cycle of pods.
xxx failed to do so and 90 No. of bathtubs (1600 x 700) were received with visible defects and quality that doesn’t meet the industry standard. We have raised this matter and its criticality in our letters ref: xxx dated 27thApr 20, xxx dated 14 May 20 and xxx dated 21stMay 20 requesting for the replacement of defected bathtubs to avoid disruption of the production.
We are unable to complete the pods without these bathtubs and our production stopped.
Till date no replacement has been done and these bathtubs are impacting the completion of Phase A and B pods. We remind you that from the date we receive the bathtubs, we will need 12 working days at a minimum to finish each pod.
Consequently, Xxx shall not be responsible for the failure of xxx in supplying the requested Free Issue Materials to maintain production. We therefore notify you that any delay that occurs is the sole responsibility of xxx who will bear all the consequences.
We further reserve our right to claim for an Extension of Time resulting from the lack of availability of free issue material affecting production.
On behalf of xxx LLC
xxx
Project Manager