Date: xxx
Ref. xxx
Kind Attn: Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotels Building
Plot No.: xxx at Al Barsha 1st, Dubai
Subject : Fire alarm cable pulling.
Dear Mr.Tahir,
We would like to inform you that we already started the tile work 2nd floor and would like to intimate the following.
- Any kind of cable either fire alarm or BMS or requirement of the Cad Emirates /BMTC/ASPIRE or MEP to be complete before tiling.
- In case of your pipe damage or closed or any additional requirement to be asserted uncompleted without fail. Prior to the tile at 2nd floor & on words floor above.
So, we cannot hold the tiling work and have seen that fire alarm cable has not be pulled till that.
Regards,
For xxx Contracting L.L.C
xxx
General Manager