FINAL HANDING OVER SNAGS

Keys Handing over
Keys Handing over

M/s xxx Property Investment

P.O Box xxx,Dubai,UAE

Tel:  xxx

Fax: xxx

Attention :         Mr. xxx

                         Project Coordinator

Project             : Multi-Use Complex ( xxx Hotel ) on Plot No. xxx

                         at Al Barsha First, Dubai

Subject            : FINAL HANDING OVER SNAGS

Dear Sir,

With reference to the mentioned project, subject, and Letter of Award (LOA) Ref: xxx dated 29th August xxx, and in response to the snags comments, herein we would like to highlight as follows:

DESCRIPTIONSNAGACTION
365 RestaurantsBuffet skirting has bubbles / cracks that needs to be changedThe bubbles / cracks are resulted due to misusage by the Hotel Staff.  The solid wood shall not be cleaned by liquids, therefore this snag is out of our responsibilities.
Floor parquet gets damaged continuouslyAll damages have been rectified
Business CenterOutside wall wooden panel came outAll wooden panels have been re-fixed properly
Carvin Cajun RestaurantsBuffet wooden counter has cracksMisusage by staff refer the above clarification

In view of above, we consider all snags have been responded.

Kind Regards,

For: xxx Interiors LLC

xxx

Commercial Dept. In-Charge

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.