Delivered Pods spoiled by others

Delivered Pods spoiled by others

Ref                                         : XXX/1437/XXX-050

Date                                      : 03th July XXX

To                                           : XXX ENGINEERING AND CONTRACTING

Attention                            : Mr. xxx

Project                                 : XXX STAFF ACCOMADATION

Subject                                 : Delivered Pods spoiled by others          

Dear Mr. xxx,

I would like to highlight again regarding our pods getting damaged and spoiled by other subcontractors. We are struggling to keep our pods in good condition once it is delivered and installed at site. They MEP contractor are not following any guidelines on how to do their work without damaging and spoiling others scope of work. 

They have to clean their left over’s and leave it as it was when they started the work. As mentioned in previous correspondence Unipods cannot take the responsibility of other unprofessional activities in our pods.

Please find the attached Pictures for your reference about the subject mentioned in this letter.

Regards,

xxx

Projects Manager

Leave a Reply

Your email address will not be published. Required fields are marked *