advance payment

Default on Progress Payment and impact on site progress

Our Ref: xxx

Date: xxx

To                    :           xxx Contracting Middle East,

                                   P.O.Box xxx,

                                   Dubai, UAE 

Attention          :           Ms. xxx

                        :           Project Director

Project             :           xxx Tower Views, Dubai

Subject                 : Default on Progress Payment

Dear Mr. xxx,

This is to put on record that xxx is in default on Xxx progress payment against IPA No. 7 for the month of February 2020 submitted on the 23rd of February xxx.  The due date for issuing the PDC was 6th of April 2020.  Your default in issuing our progress payment PDC is one month.

Additionally, certification for the works done for the month of March xxx through IPA No. 8 submitted on the 23rd of March xxx is in delay, as the due date of certification is 20th of April xxx.

Xxx will not be liable for any delay to the progress of works caused by your default on your contractual liabilities, and we reserve our right for an Extension of Time (EOT) equivalent to the same number of days by which our interim payment is delayed.

We urge you to settle our overdue progress payments immediately.

On behalf of xxx LLC

xxx

Project Manager       