Date: xxx
Ref. xxx
To: M/s. xxx , Metal Wowks
Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai
Subject | : | Regarding cost variation for modification and main entrance area Glazing work around the revolving door at G.F |
Dear Engr. Mansour ,
With reference to above there is a change in your tender drawing and the reversed drawing. Furthermore, you executed the work for the revised drawing but you didn’t submit the cost impact for positive and negative by assessing impact for drawings.
So this is for your kind information that provide cost variance by comparing approved drawing and revised drawing as soon as possible before to submit your final invoice
Regards,
For xxx Contracting L.L.C
xxx
Project Manager