Tower 2B Site Not Ready

Project Manager

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Tower 2B Site Not Ready Dear Sir, Further to our on-going works for the Tower 2B, we would like to draw your… Continue reading Tower 2B Site Not Ready

Purchase Order for Tower 2B – Levels 1 to 14

Variation notification

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Purchase Order for Tower 2B – Levels 1 to 14 Dear Sir, We refer to the Purchase Order reference xxx dated 5th… Continue reading Purchase Order for Tower 2B – Levels 1 to 14

Missing Materials for Tower 2B – Levels 15 to 20

Engineer's Instruction

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Missing Materials for Tower 2B – Levels 15 to 20 Dear Sir, We refer to the above subject and would like to… Continue reading Missing Materials for Tower 2B – Levels 15 to 20

Tower 10B – Tall Units (Kitchen Cabinets)

Kitchen Cabinet

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Tower 10B – Tall Units (Kitchen Cabinets) Dear Sir, We refer to the above subject and to the… Continue reading Tower 10B – Tall Units (Kitchen Cabinets)

Missing Materials for Tower 2B

Snagging and De-snagging

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Missing Materials for Tower 2B Dear Sir, We refer to the above subject and would like to draw… Continue reading Missing Materials for Tower 2B

Missing & Damaged Materials for Tower 2B – Levels 1 to 14

Engineer's Instruction

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Missing & Damaged Materials for Tower 2B – Levels 1 to 14 Dear Keiran, We refer to the… Continue reading Missing & Damaged Materials for Tower 2B – Levels 1 to 14

Approved Shop Drawings

structural-shop-drawing

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx F. xxx M. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject           :           Approved Shop Drawings Dear Ms. xxx, We refer to our email dated 6th September xxx in relation to… Continue reading Approved Shop Drawings

Quotation for Bulkhead Treatment at Townhouse – Rev. 1

ceiling-works

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Quotation for Bulkhead Treatment at Townhouse – Rev. 1 Reference       :  Transmittal R8-1573 dated 2nd February 2016       Dear Sir, Further to… Continue reading Quotation for Bulkhead Treatment at Townhouse – Rev. 1

Release of Payment in Relation to the Kitchen Cabinet and Wardrobes

advance payment

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Release of Payment in Relation to the Kitchen Cabinet and Wardrobes Dear Sir, We refer to our Subcontract Agreement with M/s… Continue reading Release of Payment in Relation to the Kitchen Cabinet and Wardrobes

Transmittal R8-1573 dated 2nd February xxx   

Undertaking Letter

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Quotation for Bulkhead Treatment at Townhouse Reference       :  Transmittal R8-1573 dated 2nd February xxx         Dear Sir, Further to the reference above,… Continue reading Transmittal R8-1573 dated 2nd February xxx   