Conditional TOC – Starting of Defects Liability Period

Warranties and Operating & Maintenance Manuals

Warranties and Operating & Maintenance Manuals

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject:                Conditional TOC – Starting of Defects Liability Period

Dear Mr xxx,

We are in receipt of your letter No xxx dated 03 July xxx with Subject “Conditional TOC – Starting of Defects Liability Period “and we hereby record our response as follows.

It is astonishing that while this TOC is dated 02 March xxx, the Main Contractor has waited over four months to provide Xxxx information of its existence, especially considering that the release of our retention money is directly linked to the date of the TOC.

We have reviewed the contents of your letter and the contents of its attachments and Appendices D, E and F (A, B, and C are omitted by the Main Contractor), and have not found any pending actions by Xxxx. The following is a detailed summary response:

Point #1: Completion of Outstanding works.

Point #2: Summary of rectification for outstanding snags as recorded vide AQCRs/SQCRs

Point #3: Pending AQCR/SQCR approval

Point #4: Submission of As-built drawings, Training Manual, and Operation & Maintenance Manual

Point #5: Rectification and close out of all outstanding NCRs

Point #6: Attic stock material handover

Point #7: Schedule of the Rectification of all current defects and defects if any after taking over.

Point #8: PQA Handing over of remaining Apartments to Emaar.

Point #9: Submission of Original Warranties.

Point #10: System Maintenance (as applicable).

Based on the above, there are no pending actions to be performed by Xxxx at site at this time.

We again reserve our right to take any action against you until such time as our long overdue payment for completed and fully certified works has been released in full. We further reserve our right to claim for the cost of all the workforce which Xxxx was instructed to maintain on site from 17 June xxxx (original completion date of the Main Works) until 02 March 2023, which is the date of the TOC.

We equally reserve our right to suspend the execution of the Sub‐Contract Agreement until full payment of our outstanding dues in reference to Article 247 of the UAE Civil Code and/or to terminate the Sub‐Contract Agreement in view of your uncontested and unjustified default pursuant to Article 272 of the same Code.

In the same line, Xxxx will not be held liable for any direct or indirect impact on the site progress and work completion. These liabilities reside with XXXX.

All our rights are reserved.

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       