Ref: xxx
Date: xxx
To:
P.O Box: xxx
Tel: xxx, Fax: xxx
Project : 2B+G+7 Residential Building, ICP1 CBD C01, International City
Client : M/s xxx Properties Ltd
Consultant : M/s xxx Engineering Consultant.
Subject: Clearance for Garbage the chute work.
Dear Sir
With reference to the above mentioned subject, we would like to inform you that, our site is ready for the garbage work up to 6th floor, so kindly make your work schedule and start the work within 2 days.
In this regards your cooperation is highly appreciated.
For xxx Contracting LLC
xxx
General Manager
Related Articles
- Serious Delays in Delivery of Pods Due to Poor Quality of Vanity Marbles – Serious Delays in Delivery of Pods due to Poor quality of Vanity Marbles
- Shaft Closing Approval from 2nd Floor to 13th Floor and Issue Future Access – shaft closing approval 2nd floor
- Regarding Slab Cutting /core Cutting Issue and Your Letter
- Tile Delivered Without Any Pre Information
- Bathtub Overflow Fittings Rejection by Consultant