Bathroom Pods Program of Works

Critical Path

Critical Path

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject            :           Bathroom Pods Program of Works

Dear Mr. xxx,

We refer to your letter xxx. Thank you for your comments. Please note we have reviewed your comments and respond, point by point (in the same sequence as your comments), as follows:

  1. Start date of second batch of shop drawings:

This activity has been brought forward. Please note that it is contingent upon receipt of “INFORMATION FOR – xxx” (Activities xxx, xxx) which XXX requested to be on 24 April. After this activity we submit our superimposed plans (if necessary; they have already been submitted) and then the consultant will design the tile layouts based on our superimposed layouts (please see next point).

  1. Narrative: We would be happy to discuss this point during the progress meeting so that all parties involved are aware and understand the sequence of work.
  1. Logistics Plan: A draft was submitted to XXXConstruction Manager and is being finalized at the moment.
  1. Activity Descriptions: We have included the towers and levels for each activity and will do the same for the Inspection/Handover and Commissioning once those dates are clarified by xxx. Please clarify how XXX would like  to include Zones and Work Trades in their schedule.                                                                

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       