Date: xxx CC/AP/MG/07/16 Kind Attn: M/s Strong Plant Project: 2B + G + 14 + Lower Roof Hotel Building Plot No.: 373-1297 at Barsha, Dubai Subject: Our confirmation of your parking fees and Dewatering NOC Renewal Dear Sir, With reference to above mentioned subject, we would like to confirm that the parking fees… Continue reading Our confirmation of your parking fees and Dewatering NOC Renewal
Author: Md Abu Zaed Khan
Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.
Provide Roof Coordination Drawing and Loading for MEP Equipment
Date: xxx CC/AP/MG/06/16 Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: 373-1297 at Al Barsha 1st, Dubai Subject: Provide Roof Coordination Drawing and Loading for MEP Equipments Dear Mr. xxx, With reference to above mentioned subject, as we discuss since many months to provide roof… Continue reading Provide Roof Coordination Drawing and Loading for MEP Equipment
Dewatering Pit No. 1 is break down
Date: xxx CC/AP/MG/05/16 Kind Attn: M/s. Strong Plant Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: 373-1297 at Al Barsha 1st, Dubai Subject: Dewatering Pit No. 1 is break down Dear Sir, With reference to above mentioned subject, kindly send your team to active dewatering pit no. 1 as… Continue reading Dewatering Pit No. 1 is break down
Pick-up in City Max Site Mechanical Problem (2 nos.)
Date: xxx CC/AP/MG/04/16 Kind Attn: TRANSPORT INCHARGE Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: 373-1297 at Barsha, Dubai Subject: Pick-up in City Max Site Mechanical Problem (2 nos.) Dear Sir/Ma’am, With reference to above mentioned subject, kindly note the following: Single seat Pick Up: Alternator bearing damage and… Continue reading Pick-up in City Max Site Mechanical Problem (2 nos.)
Re-route your Dewatering Line
Date: xxx CC/AP/MG/03/16 Kind Attn: M/s. Strong Plant Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: 373-1297 at Barsha, Dubai Subject: Re-route your Dewatering Line Dear Sir, With reference to above mentioned subject, all the permission was granted outside of plot limit by Drainage Department to your company and… Continue reading Re-route your Dewatering Line
Road Closing Permission
Date: xxx CC/AP/MG/02/16 Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject: Road Closing Permission Dear Sir, With reference to above mentioned subject, kindly required update or send documents to us for submission to RTA of road closing permission since… Continue reading Road Closing Permission
Dewatering Existing Line has to be redirected from Plot No. 373-1298
Date: xxx CC/AP/MG/01/16 To: M/s. Strong Plant Project: 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject: Dewatering Existing Line has to be redirected from Plot No. 373-1298 Dear Sir, With reference to above mentioned subject, kindly received the attached letter from Consultant of neighbor… Continue reading Dewatering Existing Line has to be redirected from Plot No. 373-1298
Not to proceed for this project
Date: xxx CC/269/SF/01 Kind Attn: M/s Strong Force Project: 2B + G + 14 + Lower Roof Hotel Building Plot No.: 373-1297 at Barsha, Dubai Subject: Not to proceed for this project Dear Sir, With reference above, please do not proceed further regarding this project since there will be serious consequences with our existing contractor… Continue reading Not to proceed for this project
Very serious issue may lead termination of the project or part of the project.
Date: 27.07.17 To : xxx Contracting Kind Attn : Mr. xxx Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject : Very serious issue may lead termination of the project or part of the project. Dear all concerned, With reference above, May face the… Continue reading Very serious issue may lead termination of the project or part of the project.
Regarding Confirmation and No –Objection to Remove the Tower Crane Support
Date: xxx To : xxx Contracting Kind Attn : Mr. xxx Vangani /Mr. xxx Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject : Regarding Confirmation and No –Objection to Remove the Tower Crane Support @ 3rd Flr. and same System and Drawing can… Continue reading Regarding Confirmation and No –Objection to Remove the Tower Crane Support