Date: xxx Ref: xxx To : M/s. xxx Interiors Project : 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : Contract Document and additional attachment and other issues. Dear Sir, With the reference to the above subject, we are sending you the following: Collection of… Continue reading Contract Document and additional attachment and other issues.
Author: Md Abu Zaed Khan
Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.
intimation to collect Contract agreement and instruction for submittals
Date: xxx Ref: xxx To : M/s. xxx Interiors Project : 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject : intimation to collect Contract agreement and instruction for submittals Dear Sir, With reference to the above, we would like to intimate you that the contact… Continue reading intimation to collect Contract agreement and instruction for submittals
LPO Terms and Conditions for interior Fitout work
Date: xxx Ref: xxx To: M/s. xxx Interiors Project: 2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject: LPO Terms and Conditions Dear Sir, We have received the letter of Nomination Ref: AP/269/299 Dated xxx, further to which please find below LPO terms and… Continue reading LPO Terms and Conditions for interior Fitout work
Regarding inspection approval by Hilti for the closing of penetration
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Regarding inspection approval by Hilti for the closing of penetration Dear Mr.xxx, With respect to above I have given the sample draft for every inspection that… Continue reading Regarding inspection approval by Hilti for the closing of penetration
Fire alarm cable pulling
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Fire alarm cable pulling. Dear Mr.Tahir, We would like to inform you that we already started the tile work 2nd floor and would like to intimate… Continue reading Fire alarm cable pulling
Issue of MEP (Formal reminder)
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Issue of MEP (Formal reminder) Dear Mr.Tahir, With reference to the above mentioned subject please find the followings. Revised Corridor coordination drawing not yet submitted. We… Continue reading Issue of MEP (Formal reminder)
Opening Size and location
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Opening Size and location Dear Sir, With reference to the above, we would like to inform you that, we already finished the block work and plaster… Continue reading Opening Size and location
Regarding RMU room drawing
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Regarding RMU room drawing Dear Sir, As we received the RMU room drawing from you , and note the following instructions which you have been delivered… Continue reading Regarding RMU room drawing
Regarding minutes of meeting held on dated xxx and the pending MEP work which are awaited to address
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Regarding minutes of meeting held on dated xxx and the pending MEP work which are awaited to address Dear Sir , With reference to the above,… Continue reading Regarding minutes of meeting held on dated xxx and the pending MEP work which are awaited to address
Regarding Submission of variation for GRAMS and for other items
Date: xxx Ref. xxx Kind Attn: Mr. xxx Project: 2B + G + 14+ Lower Roof Hotels Building Plot No.: xxx at Al Barsha 1st, Dubai Subject : Regarding Submission of variation for GRAMS and for other items Dear Mr Tahir, With reference to above we would like to inform you that we are waiting… Continue reading Regarding Submission of variation for GRAMS and for other items