Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing

Shop Drawing

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject    : Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing. Dear Sir, With reference to the above, we intimated to raise… Continue reading Regarding Non Compliance Report by reducing the architrave size and not matching with approved drawing

Regarding non submission of advance payment invoice and bank guaranty against advance payment.

Advance-Payment-Bank-Guarantee

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject   : Regarding non submission of advance payment invoice and bank guaranty against advance payment. Dear Sir, With reference to the above, we would like to inform you… Continue reading Regarding non submission of advance payment invoice and bank guaranty against advance payment.

To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room)

False ceiling work

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject       : To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room) Dear Sir, With reference to the above, we… Continue reading To provide clearance for the False ceiling work in guest room passage in   typical floor. (Mock up room)

Regarding door frame sample and our tiling work under hold issue

fixing the floor tile

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     : Regarding door frame sample and our tiling work under hold issue Attention to: – MR. Dainel With reference to the above mentioned subject, as we requested… Continue reading Regarding door frame sample and our tiling work under hold issue

Regarding collection of the documents and other concern

subcontractor contract agreement.

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     : Regarding collection of the documents and other concern Attention to: – MR.Dainel With reference to the above mentioned subject, we would like to inform the followings.… Continue reading Regarding collection of the documents and other concern

Contract Document transmission for signature and stamp and approve of the Civil       defense door material and Dubai civil  defense license

delivery of Tiles and cheque copy.

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     : Contract Document transmission for signature and stamp and approve of the Civil       defense door material and Dubai civil  defense license Dear Sir, With reference to the… Continue reading Contract Document transmission for signature and stamp and approve of the Civil       defense door material and Dubai civil  defense license

Your ref. HC-CM: AL BAR-CL-02 dtd. 09.05.17 and our issue

Reply - Notice of Delay

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     : Your ref. HC-CM: AL BAR-CL-02 dtd. 09.05.17 and our issue In reply of your communication contains, find our disagreement based on time-lapsed and your denial now… Continue reading Your ref. HC-CM: AL BAR-CL-02 dtd. 09.05.17 and our issue

Regarding our query to M/s xxx to fix the plywood support inside the partition wall and their reply

dry wall partition works

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     :Regarding our query to M/s Gypsemna to fix the plywood support inside the partition wall and their reply Dear Sir, With reference to the above, we requested… Continue reading Regarding our query to M/s xxx to fix the plywood support inside the partition wall and their reply

Your shop drawing submission for joinery and doors on dated xxx

Shop Drawing

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     : Your shop drawing submission for joinery and doors on dated xxx Dear Sir, With reference to the above, regarding your transmittal form and submittal ref no.cm-al-bar-269-hc-tr001on… Continue reading Your shop drawing submission for joinery and doors on dated xxx

immediate submission of shop drawings and materials to avoid delay in partition work and coordination

Shop Drawing

Date: xxx Ref no: xxx To             :M/s xxx Center Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject     :Regarding immediate submission of shop drawings and materials to avoid delay in partition work and coordination Dear Sir, With reference to the above, we would like to… Continue reading immediate submission of shop drawings and materials to avoid delay in partition work and coordination