SITE MEETING

Action Plan – Long Lead Items (Final order)

Our Ref: xxx

Date: xxx

To                    :           xxx Mideast

                                   Oman Branch

Attention          :           Mr. xxx Sing

Project             :           xxx Building, Oman

Subject                 : Action Plan – Long Lead Items (Final order)

Our references

  1. Xxxx letter ref: xxx dated 9th April xxx
  2. Xxxx letter ref: xxx dated 19th April xxx
  3. Xxxx letter ref: xxx dated 26th April xxx
  4. Xxxx letter ref: xxx dated 17th May xxx
  5. Xxxx letter ref: xxx dated 1st June xxx
  6. Xxxx letter ref: xxx dated 10th June xxx

Dear Sir,

We refer to our above correspondence (ref: a to f) and numerous communications related to approval of long lead items. Please note till date we haven’t received official instruction to proceed with procurement of items related to our scope of works, as agreed during meeting at site office dated 18th December 2019.

As highlighted on several occasions, we cannot proceed with order of many items with conditional approvals (i.e. Subject to Hotel operator’s review & approval). We still not received single response to our above correspondences in this regards, however cannot hold the order further considering the site progress.

This letter serve to inform you officially that, we are proceeding with the order of the below long lead items in the absence of your instruction and hold you solely responsible for any changes at a later stage. 

Item DescriptionsManufacture / Supplier
Wall Hung Water Closet
Item Ref: 2200090000+0063890000
xxx
Under Counter Wash Basin
Item Ref. 338490000
xxx
Ablution Spray
Item Ref:27513001
xxx
Basin Mixer
Item Ref: 2332800
xxx
Shower Mixer
Item Ref. 32821000
xxx
Shower System
Item Ref. 27389001
xxx
Linear Shower Drain
Item Ref: SS Grade 316
xxx
Towel Holder
Item Ref. 0404.604-30
xxx
Tissue Dispenser
Item Ref: 0404.131-30
xxx
Sanitary Bag Holder
Item Ref: 0405.209-30
xxx
Toilet Brush Holder
Item Ref:0404.040-30
xxx
Robe Hook
Item Ref: A1320A
xxx
Double Toilet Paper Holder
Item Ref: AV426D
xxx
Toilet Paper Holder
Item Ref: AH925X
xxx
Soap Basket
Item Ref. A1351A
xxx
Crystal Shelf
Item Ref: AV408B
xxx
Hinged Grab Bar
Item Ref: AH997C+AH9K1A
xxx
Wall Hung Water Closet
Item Ref:1VSHE00
xxx
Wall Hung Wash Basin
Item Ref:1LAHN00
xxx
Bottle Trap
Item Ref: Pex-461-1-1/4-CP
xxx
Floor Outlet
Item Ref: AQD-FC051-F-SS
xxx
Flush Mechanism
Item Ref: Sigma 30
xxx
Magnifying Mirror
Item Ref:132201172
xxx
Shower Curtain Rod
Area:Type:02 Disabled Pods
H-xxx
Basin mixer 
Item Ref: (H50GBS01)
xxx

Please note, the minimum lead time of the above items will be 10 to 12 weeks and pods delivery schedule will be subsequent to actual material delivery and production time. 

Should you object to the above, please issue your instruction by return within next 24 hours, if not we will consider your acceptance on the above to proceed with final order.

Thanks,

On behalf of Xxx LLC

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *