WATER DISTRIBUTION SYSTEM INSTALLATION CHECK LIST

Method Statement Title: Installation of Chilled Water Pumps

Method Statement Title: Installation of Chilled Water Pumps

  1. Scope
  1. This method statement applies to installation of chilled water pumps and associated valve package.
  • Purpose
  • Purpose of this method statement is to outline the method of storage, handling and installation of chilled water pumps and valve package.
  • Material
  • Pump and motor assembled on a common base frame, coupled using suitable coupling arrangement by the manufacturer.
  • Isolation valves, strainers, NRV, flexible connectors and piping accessories as per approved submittals.
  • Pump foundation as per approved drawings.
  • Method
  • Receiving
  • When received at site, each pump shall be checked for quantities, model number, physical damages, etc., and notify supplier of any discrepancies for suitable rectification or replacement.
  • Valves and other accessories shall be checked for size, model and quantity. Receiving inspection shall be conducted by the storekeeper, engineer and QC engineer, which shall be documented.
  • Valves shall be segregated as per sizes/models and stored on racks within a covered store.
  • Any items found damaged or not found suitable as per the project requirements shall be quarantined. Non-compliant material shall be clearly marked and stored separately to prevent any inadvertent use until returned to vendor.
  • Storage
  • Upon completion of receiving QC inspection, the pumps will be segregated model/size wise and stored accordingly for easy retrieval.
  • Pumps shall be stored on a flat surface in well ventilated and covered storage area.
  • Inlet and outlet flange blanks shall not be removed until ready for connection to pipe work.
  • Manufacturer’s instruction shall be strictly followed as applicable.
  • If the pumps are stored for longer periods the shaft shall be periodically rotated.
  • Preparation
  • The foundations designed to meet the vibration and sound control requirements shall be provided my Main Contractor. Inertia bases will be supplied along with vibration isolators.
  • Check and ensure that the shop drawings used are latest and approved for construction.
  • ETA will co-ordinate the location of foundation as per approved shop drawings.
  • Co-ordinate with the main contractor to ensure that the foundations/concrete filling to inertia bases made as per approved shop drawings.
  • The foundation surface shall be flat and level and smoothly finished top surface.
  • Check co-ordination with other services prior to the installation.
  • Check the piping support locations and cable tray routing locations in co-ordination with pump and piping layout and ensure they are not obstructing the space around pump.
  • Ensure easy accesses and sufficient clearance for servicing and maintenance i.e, for replacement of pump, motor, cleaning of strainer, valves etc.
  • Installation
  • Mark the locations of the pump base frame.
  • Install the inertia base/pumps as per attached Annexure-I.
  • Shift the pumps to the place of installation in safe manner. Use hand trolley/folk lift/crane as applicable/required as per site conditions.
  • Alignment of coupling arrangement between motor and pumps, after pump installation shall be rechecked by the pump supplier before testing.
  • Ensure proper coupling guards are provided, where applicable.
  • Complete the piping and valve package installation as per approved drawings. Remove the ends caps fixed on the inlet and outlet flanges.
  • Install the electrical power connections as per approved drawings and test for continuity.
  • Provide grounding wiring as per approved drawings/manufacturers instruction.
  • Follow the manufacturers instructions while installing the pump.
  • Inspection
  • After completion of pump installation and piping connections, QC inspection shall be carried out as per pump installation check list.
  • “Work Inspection Request” shall be raised for consultants inspection.
  • Safety
  • All safety precautions shall be followed as per established project safety plan and procedure.
  • Only experienced and skilled technicians shall be engaged for carrying out pump installation work.
  • The people involve din the installation shall use PPE such as safety helmets, safety shoes, harness, gloves, etc., as required.
  • Safety officer shall check and ensure that all safety precautions are followed.
  • Safety officer shall check and ensure that all scaffolding and ladders used at site are having duly signed tags.
  • References
  • Manufacturers catalogue.
  • Approved chilled water pump submittals.
  • Shop drawings.
  • Specification Section 15700.
  • Records
  • `Work Inspection Request’ duly signed by the Consultant’s for installation.

8.2       Pump installation check list.