delivery of Tiles and cheque copy.

Regarding mutual consensus for payment to supplier or sub-contractor.

Date: xxx

Ref: CC/269/CM/63

To                       : M/s. xxx, Dubai, UAE

Kind Attn          : Mr. xxx

Project         : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E.

Subject                :Regarding mutual consensus for payment to supplier or sub-contractor.

Dear Sir,                          

With reference above, we would like to inform you that it was mutually agreed that City Max will support with our supplier and sub-contractors payment to support the   project and continue the activities with direct payment to supplier and sub-contractor as main contractor suffering cash flow issue due to variation and project prolongation.

Now the payment against our invoice the VLM and Plaster material supplier not released till date as well as the payment/ cheque copy to   the steel supplier also not yet released.

So, the RCC slab work, plaster and PT work  are totally under hold and our office instructed me that client is paying directly as we signed the mutual  agreement  and  submitted the required documents and that will be deducted in future invoices.

Kindly note that works under hold and we are waiting, make it clarify that you are arranging the cheque for steel as well as you’re paying directly to VLM and Plaster material supplier from our satisfied invoice.

Please make it clear for the pending issue with you as work is under hold at site and we are waiting for the response from your end.

This is for your information and to do need full to avoid further delay or reply.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager