METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION Material to be used: NEPRO / PIPES: Approved (Trans # M-088) NAMAT-PVC FITTINGS: Approved (Trans # M-076) Summary: This Method of Statement includes all the underground sewer pipe installation. 1. Procedure Excavate trenches to provide a clearance 300mm on each of the pipe. Bedding to be… Continue reading METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION
Month: October 2022
METHOD OF STATEMENT FOR PLUMBING FIXTURE INSTALLATION
METHOD OF STATEMENT FOR PLUMBING FIXTURE INSTALLATION Open an approved shop drawings. This shop drawing consist of approved toilet details and floor plans. Assemble plumbing fixtures and trim, fittings, faucets, and other components according to manufacturers’ written instructions, approved shop drawings, and referenced standards.For Water Closet:Secure approved material inspection request (MIR) for the WC.Recheck the… Continue reading METHOD OF STATEMENT FOR PLUMBING FIXTURE INSTALLATION
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET Open an approved shop drawings. This shop drawings consist of approved Toilet details and mechanical pipe sleeves location for both indoor unit refrigeration pipes and sanitary fixtures ventilation. Block work (except the shaft walls) and water proofing activity should be done first before installation. Waiting… Continue reading METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR MECHANICAL WORKS FOR SANITARY DRAINAGE
METHOD OF STATEMENT FOR MECHANICAL WORKS FOR SANITARY DRAINAGE Scope: This method of statement applies to mechanical works for sanitary drainage of buildings. Purpose: The basis of construction /installation for effective and qualified results Significant materials needed: Approved shop drawing (At site) PVC schedule 40 pipes and fittings (Trans.# ) PVC Joining Compounds and cleaner… Continue reading METHOD OF STATEMENT FOR MECHANICAL WORKS FOR SANITARY DRAINAGE
METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION
METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION Open an approved toilet detail shop drawing. This drawing should be accompanied with the approved location of mechanical pipe sleeves for both A/C indoor unit refrigeration tubes/pipes and sanitary fixtures ventilation. Installation of pipes should be done after the block work inside the toilet. Locate the pipe… Continue reading METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION
METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION INSIDE THE TOILET Open an approved toilet detail shop drawing. This drawing should be accompanied with the approved location of mechanical pipe sleeves for both A/C indoor unit refrigeration tubes/pipes and sanitary fixtures ventilation. Installation of pipes should be done after the block work inside the toilet.… Continue reading METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION
METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION Summary: This Method of Statement includes all the underground sewer pipe installation. 1. Procedure Excavate trenches to provide a clearance 200mm on each of the pipe. Bedding to be compacted in layers not exceeding 150mm to give uniform bed. Lay the pipe directly on the bedding.… Continue reading METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION
METHOD OF STATEMENT FOR ROOF WATER TANK INSTALLATION
METHOD OF STATEMENT FOR ROOF WATER TANK INSTALLATION Open an approved shop drawing for water tank location at the roof. Tanks to be installed should have passed the leak test inspection and QC inspection approval (i.e. no defects). Construct concrete pad with at least 10cm thick with 10 cm excess from the bottom sides of… Continue reading METHOD OF STATEMENT FOR ROOF WATER TANK INSTALLATION
METHOD OF STATEMENT ELECTRICAL UNDERGROUND DUCTS INSTALLATION
METHOD OF STATEMENT ELECTRICAL UNDERGROUND DUCTS INSTALLATION 1. Procedure Approved type of PVC pipe for electrical use will be ordered and supplied to site. The width of the trench for the electrical pipe will be as small as practicable with sides vertical. Mud, rock projections, boulders and hard spots will be removed from the trench… Continue reading METHOD OF STATEMENT ELECTRICAL UNDERGROUND DUCTS INSTALLATION
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET Open an approved shop drawings. This shop drawings consist of approved Toilet details and mechanical pipe sleeves location for both indoor unit refrigeration pipes and sanitary fixtures ventilation. Block work (except the shaft walls) and water proofing activity should be done first before installation. Waiting… Continue reading METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET