METHOD STATEMENT FOR THE JACK PROPPING SUPPORT AT BASEMENT 1 SLAB

Purpose of WorkThis work procedure describes the method to be adopted for Jack Propping Support at Basement 1 Slab as shown in thedrawings and as directed by the engineer in charge. Equipment’s Required U – Jack Vertical Slab Base Plate Man Power DeploymentsStaff Details: Project manager Project Engineer Q/A –Q/C Safety Officer ForemanLabour Details: Shuttering Carpenter – 10 nos. Helpers […]

METHOD STATEMENT FOR THE CONCRETING at RAMP SLAB

Purpose of WorkThis work procedure describes the method to be adopted for Concreting Work at Ramp Slab as shown in the drawings and as directed by the engineer in charge. Reference Contract Specification.o C45/20 OPC (210kg)+50% GGBS(210kg) Applicable drawings.o DM Approved drawing Equipment’s Required Concrete Placer Pump with 42m arm length – 1 no. working ( 1 no. standby) Concrete […]

METHOD STATEMENT FOR THE CONCRETING of SLAB at BASEMENT 1

Purpose of WorkThis work procedure describes the method to be adopted for Basement 1 Slab Concreting Work as shown in the drawings and as directed by the engineer in charge. Reference Contract Specification.o C40/20 OPC (120kg)+70% GGBS(280KG) Applicable drawings.o DM Approved drawing Equipment’s Required Concrete Placer Pump with 42m arm length – 2 noS. working ( 1 no. standby) Concrete […]

METHOD STATEMENT FOR RAMP SLAB FORMWORK AT STARTING POINT

Purpose of work: It describes the methodology for the execution work for the Ramp Slab Formwork from Starting PointEXECUTION Surveyor has given marking for the proper measurement for the Ramp Level and Length. The slope started towards maximum 40 cm. ht. from SSL. After casting the slope area from 0.00 level to 40cm ht., we have to start wood formwork/ […]

METHOD STATEMENT FOR REPAIRING OF BULGED AREA at RETAINING WALL

Purpose of work: It describes the methodology for the execution / treatment for the Bulged Surface Area at Retaining Wall ( Ret. 3A)Reference: Project Specification Approved DrawingEXECUTIONA. Surface Preparation Surveyor give mark for the proper measurement of Retaining Wall thickness. Chipping/ Cutting / Grinding of Mark Excess Concrete will be removed to attain the proper thickness of the wall. All […]

METHOD STATEMENT FOR CONCRETE REPAIR AT RETAINING WALL using SPECTITE Swellseal Bentobar

Purpose of work: It describes the methodology for the execution for Concrete Repair at Retaining Wall with PVC Water Stopper using SPECTITE Swellseal Bentobar.EXECUTION FOR CONCRETE REPAIRING WORKA. Surface Preparation All loose materials to be removed from the surface, clean and uncontaminated. Fully clean the concrete and remove any loose or flaking concrete. Oil and grease deposits are best removed […]