Dear Sir,

We refer your letter reference xxx dated 10th June xxx regarding the additional Wooden Door Work for the Additional Villas Nos. Villa C83 – Contemporary and Villa B81 – Classical for the above referred Project and would like to inform you that the delivery and installation is as follows;

Additional VillasQty.Delivery Date Completion of InstallationRemarks
Villa C83 – Contemporary Main Door1 no.22nd June xxx (Monday)1 day duration onlyInstallation will start once we get the Approval from Delta to remove the old main door
Villa B81 – Classical14 nos.  18th June xxx (Thursday)  21st June xxx (Sunday)  –  

Should you need additional information and clarification, please do not hesitate to contact us.

This is for your information, reference and record.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC